FIRE-Final Inspection | 11/23/1999 | 11/24/1999 | 11/24/1999 | A | PASS |
Rick Jackson
|
|
|
Bob ###-#### Occupancy approved.
|
BLD-Final | 11/23/1999 | 11/24/1999 | 11/24/1999 | P | PART |
Jim Storey
|
|
|
Bob ###-#### Ceiling pod ok.
|
Fee Review-notes | 9/24/1999 | 9/24/1999 | 11/4/1999 | | DONE |
|
|
|
|
BLD-Final | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | PASS |
Jim Storey
|
|
|
bob ###-#### ok for L/C
|
FIRE-Final Inspection | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Rick Jackson
|
|
|
bob ###-#### Complete sprinklers, alarms, exit sign
|
BLD-Framing/Rough-in | 10/25/1999 | 10/26/1999 | 10/26/1999 | A | PASS |
Jim Storey
|
|
|
Bob Cafferty, ###-#### - as late in the morning as possible
|
BLD-Framing/Rough-in | 9/29/1999 | 9/30/1999 | 9/30/1999 | A | PASS |
Jim Storey
|
|
|
Bob Cafferty, ###-#### ted isabell arch to resubmit to dan stuart plan reviewed 1 hr corridoor
|
Inspection Record Card- Bld | | | 9/28/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/1999 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/28/1999 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/24/1999 | 9/24/1999 | 9/27/1999 | | PASS |
Dan Stuart
|
|
|
9/24/1999 17:37:41 DRS - activity updated through activity BLDA022 from case BLD99-02882. 9/27/99 - Routing for issuance of permit.
|
Routing - PLAN CHECK | 9/24/1999 | 9/24/1999 | 9/27/1999 | | PASS |
|
|
|
PLAN APPROVED AS NOTED AND ATTACHED. PROCESSING FOR PERMIT.
9/27/99 - Faxed & mailed copy of plan review comments to architect, Ted Isbell.
9/27/99 - Reviewed scope of work with Bill Allexander, fire code analyst, to see if fire code issues could be reviewed in filed based on my plan review comments in an effort to speed up permit issuance, or if he wanted to review the plans. He agreed that the project could be reviewed by the field inspector for code compliance.
|
Case Summary (BLD) | | | 9/27/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/27/1999 | | PASS |
|
|
|
APPROVED AS NOTED AND ATTACHED.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/1999 | | PASS |
|
|
|
Approved as noted and attached.Routing to permit desk for processing for building permit.
|
Application received | | | 9/24/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/24/1999 | | |
|
|
|
|
Meeting | | | 9/24/1999 | | PEND |
|
|
|
MET WITH TED ISBELL, HOSFORD-LARSON-RUDEEN, TO REVIEW SCOPE OF PROPOSED PROJECT AT ALBERTSON'S BENCH PLAZA. WORK CONSISTS OF NON-RATED NON-BEARING WALLS TO CREAT PRIVATE OFFICE SPACES AND SMALL CONFERENCE ROOMS ON 1ST & 3RD FLOORS. DOES NOT EFFECT TOTAL AREA; OCCUPANCY GROUPS OR OCCUPANT LOAD FOR ORIGINAL STRUCTURE & PERMITS. DOES NOT INVOLVE RATED FIRE-WALL CONSTRUCTION. CAN PROCESS AS A QUICK RESPONSE PERMIT.
|
Pending Assignment by MYS | 9/24/1999 | | | | |
Marlene Southard
|
|
|
|
Pending Assignment by MYS | 9/24/1999 | | | | |
Marlene Southard
|
|
|
|