Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD99-02888
StatusExpired
Name HILLCREST COUNTRY CLUB INC
Site Address 4610 W HILLCREST DR
Project NameHILLCREST STORAGE BLD.
Customer Number 
ePlanReviewNo
Description
HILLCREST COUNTRY CLUB * STORAGE BUILDING TO CONSTRUCT A NEW 2025 SQ.FT. SINGLE STORY, COMBINATION EXTERIOR WALLS OF CMU AND PREFABRICATED METAL STRUCTURE, TYPE V NONRATED STORAGE BUILDING FOR HILLCREST COUNTRY CLUB BEHIND THE INDOOR TENNIS COURTS. THIS PERMIT DOES NOT INCLUDE ANY OTHER STRUCTURES OTHER THAN THOUGH MENTIONED IN THIS PERMIT. SEPARATE PERMIT AND PLANS WILL BE REQUIED TO BE SUBMITTED FOR REVIEW OF STORAGE AND HOSE FENCES AND DRYING RACK. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. DRH99-0065 PC#769-99 MJP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection5/22/20005/23/20005/23/2000AFAIL
DetailsJoe Tawney
jim ###-#### Final fail C/N issued. 5/23/00 2:12:10 PM
BLD-Final5/22/20005/23/20005/23/2000AFAIL
DetailsCarl Dependahl
jim ###-#### Need other sig's. 5/24/00 11:11:50 AM
BLD-Framing/Rough-in4/27/20004/28/20004/28/2000APART
DetailsCarl Dependahl
Jim ###-#### Rec'd ARch's detail re: 1hr const...ext. side gyp. ok 4/28/00 3:05:31 PM
BLD-Framing/Rough-in4/27/20004/27/20004/27/2000PFAIL
DetailsCarl Dependahl
###-#### Need Arch's detail for 1hr walls. 4/28/00 3:00:39 PM
BLD-Framing/Rough-in4/24/20004/25/20004/25/2000PFAIL
DetailsCarl Dependahl
###-#### Need detail for 1 hr. ext. wall const. 4/26/00 11:16:38 AM
BLD-Concrete4/20/20004/21/20004/21/2000PPART
DetailsCarl Dependahl
###-####\\rebar
BLD-Framing/Rough-in3/28/20003/29/20003/29/2000PPART
DetailsCarl Dependahl
drainage around fd insp--- jim ###-#### cell Drain rock & "filter" installed. 3/30/00 10:49:58 AM
BLD-Footing3/23/20003/24/20003/24/2000APART
DetailsCarl Dependahl
perimeter insulation around the foundation jim ###-#### Slab insulated 3/24/00 2:02:34 PM
BLD-Foundation3/17/20003/20/20003/20/2000APART
DetailsCarl Dependahl
JIM ###-#### CELL FOUND Strata onsite for FDN. & cylinders. 3/21/00 4:10:42 PM
BLD-Footing3/14/20003/14/20003/14/2000PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/14/2000 at 10:47:24. Contact: ###-####. rebar work in progress special insp. to be on site Pending report & scope of work. "Strata" 3/16/00 11:29:43 AM
Telephone call  2/3/2000 DONE
called Kyle Freutel from BRS at ###-#### permit ready
Print Occupancy Form  2/3/2000 DONE
Inspection Record Card- Bld  2/3/2000 DONE
Issue PAID IN FULL permit  2/3/2000 DONE
Routing - FIRE2/2/20002/2/20002/2/2000 PASS
Plan assigned to (M_P)9/27/19999/27/19992/2/2000 PASS
DetailsMike Phillips
2/2/2000 15:09:12 M_P - activity updated through activity BLDA022 from case BLD99-02888.
Routing - PLAN CHECK10/25/1999 2/2/2000  
Plan Reviewer's activity  2/2/2000 DONE
Print Pending Permit.LaserJet4  2/2/2000 DONE
Case Summary (BLD)  2/2/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/2/2000 DONE
Plan resubmittals received  2/2/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, FORWARDED SAME TO MIKE PHILLIPS, SHEETS SD1 AND A2, 2 SHEETS EACH. 2/2/00 DAR
Plan resubmittals received  2/1/2000 PEND
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, KYLE FREUTEL, SHEETS SD1 AND A1. 2/1/00 DAR
Plan resubmittals received  12/22/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, KYLE FREUTEL, FORWARDED SAME TO MIKE PHILLIPS. 12/22/ 99 DAR
Telephone call  12/1/1999 DONE
Talked to Bill Strite. He has taken over project while Kyle is on vacation. I told him of the requirement to classify the products per Table 3-D and 3-E and he said he would do that and submit the info.
Meeting  11/24/1999 DONE
Had a meeting with Kyle Freutel and Bill Alexander to discuss the requirements for classification of the products to be stored and/or used in the building. Informed him that he needed to determine what hazard class, amount, location in building to comply with UBC/UFC Tables 3-D and 3-E.
Plan resubmittals received  11/16/1999 PEND
RECEIVED MEMO FROM BRS ARCHITECTS, KYLE FREUTEL, FROWARDED SAME TO MARLENE SOUTHARD. 11/16/99 DAR
Plan Reviewer's activity  11/12/1999 FAIL
More data needed in design. Hazardous chemicals sufficient to warent professional design for building classification. Left message for Kyle and Clinton to call me.
Plan resubmittals received  11/10/1999 PEND
WRITTEN RESUBMITTALS RECEIVED FROM BRS ARCHITECTS, KYLE FREUTEL, FORWARDED SAME TO MIKE PHILLIPS. 11/10/99 DAR
Plan resubmittals received  11/8/1999 PEND
RECEIVED PLAN RESUBMITTALS FOR BILL ALEXANDER, FORWARDED SAME TO BILL FROM BRS ARCHITECTS. 11/8/99 DAR
Plan resubmittals received  11/5/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, KYLE FREUTEL, FORWARDED SAME TO MIKE PHILLIPS. 11/5/99 DAR
Routing - FIRE10/20/199910/20/199910/25/1999 FAIL
Need fire access, hydrant location, storage information (commodities, classifications, elevations).
Plan Review Completed(1st rev)  10/25/1999 FAIL
Plan resubmittals requested  10/19/1999 FAIL
ADDITIONAL INFORMATION REQUESTED FOR FURTHER REVIEW.
Print Pending Permit.LaserJet4  10/19/1999 FAIL
ADDITIONAL INFORMATION REQUESTED FOR FOLLOW UP REVIEW.
Routing - PLAN CHECK10/6/1999 10/19/1999 FAIL
10/7/99 Mike I routed plans to fire for parking lot expansion and grading for the storage shed. KMM
ROUTING TO FIRE DEPARTMENT FOR THERE REVIEW. MJP
Routing - PLANNING10/6/1999 10/6/1999 PASS
No design review approval necessary - A zone. TKW
Cup99-00057 has been approved. BGN
Routing - PLUMBING9/30/1999 10/6/1999 PASS
no plumbing associated with this project
Routing - PUBLIC WORKS9/28/19999/28/19999/29/1999 PASS
Case Summary (BLD)  9/28/1999 PEND
Fee Review-notes9/27/19999/27/19999/27/1999 DONE
LINDA THIS PERMIT WAS SUBMITTED ALONG WITH THE PARKING LOT. I CONTACTED KYLE TO SEPARATE INTO TWO SEPARATE PERMITS. INITIAL PROJECT VALUE WHICH INCLUDED BUILDING AND PARKING LOT, WAS $135,750 ELECT. $8,000 MECH. $12,000 PLUMB. AND FIRE SPRINKLER N/A. THANKS KMM
REVISED CERT. OF VALUE FOR BLD99-02888 IS PROJECT VALUE $40,400 ELECT. $1,200 MECH. $3,000 PLUMB. AND FIRE SPRINKLER N/A BUILDING PERMIT # FOR THE PARKING LOT IS BLD99-02906. KYLE ADDED A GRADING AND DRAINAGE PERMIT FOR THE STORAGE BUILDING. THE BLD# FOR GRADING IS BLD99-02907 KMM
Plan routing begun/NEW & ADDTN  9/27/1999  
Plans ACCEPTED BY PLAN TECH  9/27/1999 PEND
REQUIRES PRE-ENGINEERED BUILDING PLANS. CONTACTED KYLE OF THIS NEED. WILL ROUTE TO PW, P&Z, AND PLAN CHECK. HOPEFULLY PRE-ENGINEERED PLANS WILL BE HERE BY THEN. PROJECT CONSITS OF THREE PROJECTS. THE NEW STORAGE BUILDING BLD99-02888, THE GRADING AND DRAINAGE FOR THE NEW BUILDING, BLD99- , AND THE PARKING LOT EXPANSION, BLD99- KMM
Received Certificate of Value  9/27/1999 PEND
SUBMITTED PLANS FOR STORAGE BUILDING AND PARKING LOT NEED TO SEPARATE OUT INTO DIFFERENT PERMITS. KMM KYLE ALSO REQUESTED GRADING PERMIT. HAD HIM FAX OVER THREE CERT. OF VALUE. ONE FOR BUILDING, ONE FOR PARKING LOT EXPANSION AND ONE GRADING PERMIT FOR THE NEW BUILDING. ALL WILL BE ROUTED ON THE SAME SET OF PLANS. KMM
Application received  9/24/1999  
Case Summary (BLD)     
Routing - PLAN CHECK2/2/2000   PEND