BLD-Final | 2/22/2000 | 2/22/2000 | 2/22/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/22/2000 at 09:11:35. Contact: ###-####. C/C #17268. 2/23/00 1:46:12 PM
|
BLD-Final | 2/10/2000 | 2/11/2000 | 2/11/2000 | A | FAIL |
Tom Arcoraci
|
|
|
###-#### AMMON See C/N. 2/14/00 2:13:50 PM
|
BLD-Framing/Rough-in | 1/5/2000 | 1/6/2000 | 1/6/2000 | A | PASS |
Jim Sly
|
|
|
###-#### Ammon. Energy code ok (pass).
|
BLD-Framing/Rough-in | 12/29/1999 | 12/29/1999 | 12/29/1999 | P | FAIL |
Tom Arcoraci
|
|
|
###-####. Not ready.
|
BLD-Framing/Rough-in | 12/28/1999 | 12/28/1999 | 12/27/1999 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/28/1999 at 10:45:23. Contact: ###-####. C/N need header @ (garage) furnace alcove.
|
BLD-Framing/Rough-in | 12/27/1999 | 12/27/1999 | 12/27/1999 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 10:43:11. Contact: ###-####. Complete prev. corr.
|
BLD-Framing/Rough-in | 12/21/1999 | 12/22/1999 | 12/22/1999 | A | FAIL |
Jim Sly
|
|
|
amon ###-#### re-insp fr C/N.. Prev. corr. & new corr. Notice.
|
BLD-Framing/Rough-in | 12/20/1999 | 12/20/1999 | 12/20/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/20/1999 at 08:26:55. Contact: ###-####. C/N: trusses, ok to insul.
|
BLD-Framing/Rough-in | 12/14/1999 | 12/15/1999 | 12/15/1999 | P | FAIL |
Wes Worcester
|
|
|
james ###-#### fr insp---- PER -AMMON CANCEL BCEC not done, previous C/N not done.
|
BLD-Framing/Rough-in | 11/23/1999 | 11/24/1999 | 11/24/1999 | A | PART |
Jim Sly
|
|
|
ammon ###-#### shear wall Shear ok C/N.. Verify (2) retro fit HD's at frame.
|
BLD-Framing/Rough-in | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | FAIL |
Jim Sly
|
|
|
Ammon ###-#### C/N.. Nail brace panels per eng. Missed straps.
|
BLD-Foundation | 11/2/1999 | 11/3/1999 | 11/3/1999 | A | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Footing | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Jim Sly
|
|
|
FOR FT INSP ROBERT-- --###-#### Not ready 10 am
|
BLD-Footing | 11/1/1999 | 11/1/1999 | 11/1/1999 | P | PART |
Jim Sly
|
|
|
re-insp ft --robert ###-#### Footing appears ok
|
Issue PAID IN FULL permit | | | 10/27/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/30/1999 | | DONE |
|
|
|
|
Telephone call | | | 9/30/1999 | | DONE |
|
|
|
Called Oasis Construction ###-####
|
Plan assigned to (DJO) | 9/27/1999 | | 9/30/1999 | | DONE |
Dan Overy
|
|
|
|
Plan assigned to (SAM) | 9/30/1999 | | 9/30/1999 | | PASS |
Steve Munroe
|
|
|
9/30/1999 14:34:28 SAM - activity updated through activity BLDA022 from case BLD99-02891.
|
Routing - PUBLIC WORKS | 9/27/1999 | 9/27/1999 | 9/27/1999 | | DONE |
|
|
|
|
Routing - PLANNING | 9/27/1999 | 9/27/1999 | 9/27/1999 | | DONE |
|
|
|
|
Application received | | | 9/27/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 9/27/1999 | 9/27/1999 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 9/27/1999 | | | | PEND |
Dan Overy
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|