DOC - Permit Finaled | 1/19/2001 | 1/19/2001 | 1/19/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 1/19/2001 2:52:54 PM
|
BLD-Final | 7/10/2000 | 7/10/2000 | 7/10/2000 | A | PASS |
Tom Arcoraci
|
|
|
L/C issued.
|
BLD-Final | 7/6/2000 | 7/7/2000 | 7/7/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 20:43:42. Contact: ###-####. NO elec. final C/N posted 7/7/00 1:48:39 PM
|
BLD-Framing/Rough-in | 2/14/2000 | 2/14/2000 | 2/14/2000 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/14/2000 at 07:52:14. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 02/14/2000 at 09:23:54.
|
BLD-Wall cover | 2/14/2000 | 2/14/2000 | 2/14/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/14/2000 at 09:26:48. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/10/2000 | 2/11/2000 | 2/11/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/10/2000 at 16:12:30. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/27/2000 | 1/27/2000 | 1/27/2000 | P | PART |
Tom Arcoraci
|
|
|
late pm Dan ###-#### ok to side 1/28/00 9:12:41 AM
|
BLD-Foundation | 10/8/1999 | 10/8/1999 | 10/8/1999 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/08/1999 at 07:54:54. Contact: ###-####.
|
BLD-Foundation | 10/6/1999 | 10/7/1999 | 10/7/1999 | A | FAIL |
Jim Sly
|
|
|
###-#### dan/cancelled by contractor
|
BLD-Foundation | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/07/1999 at 08:49:23. Contact: ###-####. C/n need mech final and misc corrections
|
Issue PAID IN FULL permit | | | 10/6/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/5/1999 | | DONE |
|
|
|
###-####
|
Plan assigned to (DJO) | 10/4/1999 | 10/4/1999 | 10/4/1999 | | PASS |
Dan Overy
|
|
|
10/4/99 09:49:10 DJO - activity updated through activity BLDA022 from case BLD99-02921.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/4/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/4/1999 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 9/28/1999 | | 10/4/1999 | | PASS |
Dan Overy
|
|
|
10/4/99 09:49:10 DJO - activity updated through activity BLDA022 from case BLD99-02921.
|
Plans ACCEPTED BY PLAN CHECK | | | 10/4/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 9/28/1999 | | 9/29/1999 | | DONE |
|
|
|
|
Routing - PLANNING | 9/28/1999 | | 9/28/1999 | | DONE |
|
|
|
|
Application received | | | 9/28/1999 | | |
|
|
|
|
Early Start Permit | | | 9/28/1999 | | HOLD |
|
|
|
early start footing and foundation see cond. pe
|
Early Start Permit | | | | | |
|
|
|
|
Routing - PLAN CHECK | 9/29/1999 | | | | PEND |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Pending Assignment by DJO | 9/28/1999 | | | | PEND |
Dan Overy
|
|
|
|
Early Start Permit | | | | | HOLD |
|
|
|
early start only see cond
|