Fee Review-notes | 12/16/1999 | 12/16/1999 | 7/24/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/14/2000 | 6/15/2000 | 6/15/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 12:35:50. Contact: ###-####.
|
BLD-Final | 6/14/2000 | 6/15/2000 | 6/15/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 16:10:13. Contact: ###-####.
|
Letter of compliance | | | 6/15/2000 | | DONE |
|
|
|
Letter of Compliance #18515 issued 6-15-00.
|
Code Occupancy Approval | | | 6/15/2000 | | PASS |
|
|
|
ALL CONDITIONS OF DRH98-00181 HAVE BEEN MET SO FINAL SIGNED OFF.
|
BLD-Final | 6/8/2000 | 6/9/2000 | 6/9/2000 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/08/2000 at 16:33:26. Contact: ###-####.
|
BLD-Final | 6/8/2000 | 6/9/2000 | 6/9/2000 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/08/2000 at 16:33:26. Contact: ###-####.
|
BLD-Footing | 3/28/2000 | 3/29/2000 | 3/29/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/28/2000 at 14:44:57. Contact: ###-####.
|
BLD-Footing | 3/28/2000 | 3/29/2000 | 3/29/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/28/2000 at 14:44:57. Contact: ###-####.
|
Inspection Record Card- Bld | | | 3/10/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/10/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2000 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/26/2000 | | 2/14/2000 | | PEND |
|
|
|
RESUBMITTALS SENT TO ENGINEERING CONSULTANT VIA PDQ., RESUBMITTALS FROM STAPLEY ENGINEERING. 1/26/00 DAR
|
Plan assigned to (MLO) | 10/4/1999 | 10/4/1999 | 2/11/2000 | | DONE |
Mike Otto
|
|
|
|
Routing - PLAN CHECK | 2/4/2000 | | 2/11/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2000 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/9/2000 | | 2/10/2000 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/9/2000 | | FAIL |
|
|
|
STRUCTURAL CORRECTION ON RESUBMITTALS. ARCHITECT NOTIFIED.
|
Routing Off Site - STRUCTURAL | 2/3/2000 | | 2/9/2000 | | FAIL |
|
|
|
SENT RESUBS TO CONSULTANTING ENGINEER VIA PDQ. 2/3/00 DAR
|
Routing - PLANNING | 1/26/2000 | | 2/4/2000 | | PASS |
|
|
|
Approved per DRH99-00140.
|
Plan resubmittals received | | | 2/3/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PETERSEN STAGGS ARCHITECTS, FORWARDED SAME TO MIKE OTTO, REVISED FUEL CANOPY DRAWINGS,FUEL CANOPY CACULATIONS,WRITTEN LINE ITEM RESPONSES FOR REVISIONS.2/3/00 DAR
|
Plan resubmittals received | | | 1/28/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PETERSEN - STAGGS ARCHITECTS, TIMOTHY STAGGS, LETTER OF RESPONSE DTD 1-27-00, REVISED SHEETS 3.0A, 3.0B, 3.1A, 3.3C, ROYSTON CUT SHEET OF COUNTERS. 1/28/00 DAR
|
Routing Off Site - STRUCTURAL | 1/13/2000 | | 1/24/2000 | | FAIL |
|
|
|
SENT PLANS AND CALCS FOR CANOPY WHICH WERE NOT INCLUDED WITH SUBMITTAL FOR MAIN BUILDING ON ENGINEERS SET ONLY. MLO
|
Plan resubmittals requested | | | 1/24/2000 | | FAIL |
|
|
|
STRUCTURAL CORRECTIONS FOR CANOPY FAXED TO ARCHITECT. MLO
|
Plan resubmittals received | | | 1/24/2000 | | DONE |
|
|
|
RECEIVED 1/21/2000 AT 4:15 PM ONE LETTER IN RESPONSE TO PLAN REVIEW COMMENTS W/ ATTACHMENTS TO INCLUDE LIST OF DRAWINGS.
THREE SETS OF STRUCTURAL RESUBMITTAL DRAWINGS.
TWO SETS SUPPLEMENTAL STRUCTURAL CALCULATIONS.
TWO SETS BUILDING ( INCLUDING MECH., ELECT. CIVIL FUEL) RESUBMITTAL DRAWINGS.
TWO SETS CANOPY DRAWINGS SHOWING COLORS TO MATCH BLDG. ROUTED TO MIKE O. KMM
|
Additional plans submitted | | | 1/13/2000 | | PEND |
|
|
|
SENT OMITTED PLANS TO CONSULTING STRUCTURAL ENGINEER VIA PDQ 1/13/00 DAR
|
Routing Off Site - STRUCTURAL | 10/22/1999 | | 11/9/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan resubmittals requested | | | 11/9/1999 | | FAIL |
|
|
|
structural corrections faxed to architect. MLO
|
Routing - FIRE | 10/22/1999 | 10/26/1999 | 10/26/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/26/1999 | | PEND |
|
|
|
PLANS SENT BACK TO PLAN REVIEW
|
Routing - PLAN CHECK | 10/11/1999 | | 10/22/1999 | | PEND |
|
|
|
REQUIRES STRUCTRUAL REVIEW BY OUTSIDE ENGINEERING. MLO
|
Routing - PLUMBING | 10/7/1999 | | 10/11/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/4/1999 | 10/4/1999 | 10/7/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 10/7/1999 | | 10/7/1999 | | PEND |
|
|
|
Revised plans indicating compliance with the Design Review conditions must be submitted to Planning Staff for review and approval (see letter in DRH99-0140 file).
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/1999 | | DONE |
|
|
|
PLANS INCLUDE PERMITS FOR BLD99-02973 (FUEL ISLAND), AND BLD99-02974 (CONVENIENCE STORE #184) AT THIS TIME MR. STAGGS DID NOT WANT TO SUBMIT FOR A GRADING AND DRAINAGE PERMIT. KMM
|
Received Certificate of Value | | | 10/4/1999 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/4/1999 | | |
|
|
|
|
Case Summary (BLD) | | | 10/4/1999 | | DONE |
|
|
|
|
Fee Review-notes | 10/1/1999 | 10/1/1999 | 10/1/1999 | | DONE |
|
|
|
|
Application received | | | 10/1/1999 | | |
|
|
|
|
Pending Assignment by MYS | 10/1/1999 | | 10/1/1999 | | DONE |
Marlene Southard
|
|
|
|
Routing Off Site - C.D.H | 9/15/1999 | 9/15/1999 | 9/15/1999 | | PASS |
|
|
|
|