Fee Review-notes | 12/6/1999 | 12/6/1999 | 7/20/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/14/2000 | 6/15/2000 | 6/15/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 12:34:05. Contact: ###-####.
|
BLD-Final | 6/14/2000 | 6/15/2000 | 6/15/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 16:08:56. Contact: ###-####.
|
Permanent Occupancy | | 6/15/2000 | 6/15/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 6/15/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8263 issued 6-15-00 to Albertson's Express Convenience Store.
|
Code Occupancy Approval | | | 6/15/2000 | | PASS |
|
|
|
ALL CONDITIONS HAVE BEEN MET SO FINAL OCCUPANCY SIGNED OFF.
|
BLD-Final | 6/8/2000 | 6/9/2000 | 6/9/2000 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/08/2000 at 16:31:51. Contact: ###-####.
|
BLD-Final | 6/8/2000 | 6/9/2000 | 6/9/2000 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/08/2000 at 16:31:51. Contact: ###-####.
|
BLD-Wall cover | 5/3/2000 | 5/4/2000 | 5/4/2000 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/03/2000 at 11:46:36. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/24/2000 | 4/25/2000 | 4/25/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/24/2000 at 14:37:51. Contact: ###-####. 16ga double studs at each holddown instaled inverted to the engineered design. requirer engineer to approve instalation or redesign for loading. all other atchments appear to be per plan. 4/25/00 11:32:56 AM
|
BLD-Foundation | 3/21/2000 | 3/22/2000 | 3/22/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/21/2000 at 14:11:41. Contact: ###-####. rebar ok pending special insp. report on concrete samples. 3/22/00 11:51:49 AM
|
BLD-Foundation | 3/20/2000 | 3/21/2000 | 3/21/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/20/2000 at 15:10:06. Contact: ###-####.
|
BLD-Foundation | 3/17/2000 | 3/20/2000 | 3/20/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/17/2000 at 15:18:23. Contact: ###-####. recieved scope of work covered by special inspection. foottings rebar ok set backs surveied in. 3/20/00 2:47:51 PM
|
(F) Reprint permit | | | 3/13/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 10/4/1999 | 10/4/1999 | 2/11/2000 | | DONE |
Mike Otto
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/11/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 2/11/2000 | | DONE |
|
|
|
Left message with amount and notified that plans were ready to pick up.kkh.
|
Routing Off Site - STRUCTURAL | 2/9/2000 | | 2/10/2000 | | PASS |
|
|
|
REMOVED MISSING SHEETS 2.0A, 2.0B. 2.4 FROM OFFICE COPY AND SENT TO ENGNIEER. MLO
|
Routing Off Site - STRUCTURAL | 1/24/2000 | | 2/9/2000 | | FAIL |
|
|
|
STRUCTURAL REVISIONS FOR STORE SENT TO ENGINEER. 2-9-00 RECEIVED CALL FROM AHJ THAT SEVERAL UPDATED SHEETS MISSING 2.0A, 2.0B, & 2.4. CONTACTED ARCHITECT. MLO
|
Routing - PLANNING | 1/26/2000 | | 2/4/2000 | | PASS |
|
|
|
Approved per DRH99-00140.
|
Routing - PLAN CHECK | 1/31/2000 | | 2/2/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/28/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PETERSEN - STAGGS, TIMOTHY STAGGS, RECEIVED A LETTER OF RESPONSE DTD 1/27/2000. SHEETS 3.0A, 3.0B, 3.1A, 3.3C, AND A ROYSTON CUT SHEET. 1/28/00 DAR
|
Routing - PLAN CHECK | 1/24/2000 | | 1/26/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
|
Plan resubmittals requested | | | 1/26/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Plan resubmittals received | | | 1/24/2000 | | DONE |
|
|
|
RECEIVED 1/21/2000 AT 4:15 PM ONE LETTER IN RESPONSE TO PLAN REVIEW COMMENTS W/ ATTACHMENTS TO INCLUDE LIST OF DRAWINGS.
THREE SETS OF STRUCTURAL RESUBMITTAL DRAWINGS.
TWWO SETS OF SUPPLEMENTAL STRUCTURAL CALCULATIONS.
TWO SETS BUILDING ( INCLUDING MECH. ELECT. CIVI., FUEL) RESUBMITTAL DRAWINGS.
TWO SETS OF CANOPY DRAWINGS SHOWING COLORS TO MATCH BLDG. ROUTED TO MIKE O. KMM
|
Routing Off Site - STRUCTURAL | 10/22/1999 | | 11/9/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plan resubmittals requested | | | 11/9/1999 | | FAIL |
|
|
|
structural corrections faxed to architect. MLO
|
Routing - FIRE | 10/22/1999 | 10/26/1999 | 10/26/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/26/1999 | | PEND |
|
|
|
PLANS SENT BACK TO PLAN REVIEW
|
Plan resubmittals requested | | | 10/22/1999 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 10/11/1999 | | 10/22/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLUMBING | 10/7/1999 | | 10/11/1999 | | PASS |
|
|
|
locate rp's over janitor sink, rp required on carbonators, sewer elevations on 1.4a and 4.1, dont match, verify.
|
Routing - PUBLIC WORKS | 10/4/1999 | 10/4/1999 | 10/7/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 10/7/1999 | | 10/7/1999 | | PEND |
|
|
|
Revised plans indicating compliance with the Design Review conditions must be submitted to Planning Staff for review and approval (see letter in DRH99-0140 file).
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/1999 | | DONE |
|
|
|
PLANS INCLUDE PERMITS FOR BLD99-02973 (FUEL ISLAND), AND BLD99-02974 (CONVENIENCE STORE #184). AT THIS TIME R. STAGGS DID NOT WANT TO SUBMIT FOR A GRADING AND DRAINAGE PERMIT. KMM
|
Received Certificate of Value | | | 10/4/1999 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/4/1999 | | |
|
|
|
|
Case Summary (BLD) | | | 10/4/1999 | | DONE |
|
|
|
|
Application received | | | 10/1/1999 | | |
|
|
|
|
Routing Off Site - C.D.H | 9/15/1999 | 9/15/1999 | 9/15/1999 | | PASS |
|
|
|
|