BLD-Final | 2/8/2000 | 2/9/2000 | 2/9/2000 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 15:58:42. Contact: .
|
BLD-Final | 2/8/2000 | 2/8/2000 | 2/8/2000 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 10:39:17. Contact: . C/W
|
BLD-Final | 2/4/2000 | 2/4/2000 | 2/4/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/04/2000 at 11:00:20. Contact: .
|
BLD-Framing/Rough-in | 12/28/1999 | 12/29/1999 | 12/29/1999 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/28/1999 at 11:32:32. Contact: . Frame ok mech ok gas co. cert on gas line resolved mech C/N previously.
|
BLD-Wall cover | 12/13/1999 | 12/13/1999 | 12/13/1999 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 10:04:23. Contact: . Nailing ok on brace panels.
|
BLD-Footing | 11/16/1999 | 11/16/1999 | 11/16/1999 | P | PASS |
Jim Storey
|
|
|
Ft. & walls ok.
|
Issue PAID IN FULL permit | | | 11/9/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/8/1999 | | 10/11/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/11/1999 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 10/8/1999 | | 10/11/1999 | | PASS |
Mike Phillips
|
|
|
10/11/1999 14:56:06 M_P - activity updated through activity BLDA022 from case BLD99-03047.
|
Plan Reviewer's activity | | | 10/11/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/11/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/11/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/11/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/1999 | | DONE |
|
|
|
|
Telephone call | | | 10/11/1999 | | DONE |
|
|
|
called ###-####
|
Routing - PLANNING | 10/8/1999 | | 10/8/1999 | | DONE |
|
|
|
|
Application received | | | 10/8/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 10/11/1999 | 10/11/1999 | | | PEND |
|
|
|
|