Fee Review-notes | 6/16/2003 | 6/16/2003 | 6/16/2003 | | DONE |
|
|
|
|
Fee Review-notes | 10/11/1999 | 10/11/1999 | 1/18/2002 | | DONE |
|
|
|
overpayment because this was split in to 4 permits I applied over payment to bld99-03116
|
Permanent Occupancy | | 1/2/2002 | 1/2/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/2/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #8975 issued to the Stinker Station/Jack in the Box (this is for the convenience store portion).
|
BLD-Final | 12/11/2001 | 12/12/2001 | 12/12/2001 | A | PASS |
Jim Sly
|
|
|
###-#### STRUCTURAL ONLY OK for Perm Occ. 12/12/2001 11:30:19 AM
|
BLD-Final | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PART |
Jim Sly
|
|
|
###-#### TOM OK for Temp Occ. C/N obtain perm Occ status within 90 days. 11/15/2001 10:08:51 AM
|
Temporary occupancy | | | 11/15/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4647 issued 11-15-01 to the Stinker Station convenience store.
|
FIRE-Final Inspection | 11/13/2001 | 11/13/2001 | 11/13/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/13/2001 2:34:06 PM Fire/life safety OK
|
BLD-Final | 11/6/2001 | 11/9/2001 | 11/9/2001 | P | NR |
Jim Sly
|
|
|
Chuck- cell ###-#### or office- ###-#### : )
|
FIRE-Final Inspection | 11/6/2001 | 11/7/2001 | 11/7/2001 | P | FAIL |
Troy Cobbley
|
|
|
provide 2nd emergency shut off switch, add extinguisher at back door in Jack's, provide all signage, add panic hard ware on double doors and west door, add exit sign, test hood 11/8/2001 10:12:31 AM
|
BLD-Framing/Rough-in | 10/23/2001 | 10/24/2001 | 10/24/2001 | A | PART |
Jim Sly
|
|
|
ceiling tom-- ###-#### cell Ceiling Stinker....OK 10/24/2001 10:18:50 AM
|
Override - Parcel Holds | | | 10/23/2001 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/10/2001 | 9/11/2001 | 9/11/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### C/N Truss bearing 9/11/2001 3:54:28 PM
|
BLD-Framing/Rough-in | 9/4/2001 | 9/4/2001 | 9/4/2001 | P | PART |
Jim Sly
|
|
|
SHEAR WALL ###-#### Shear Interior OSB at freezer wall OK. 9/4/2001 4:24:56 PM
|
BLD-Framing/Rough-in | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Jim Sly
|
|
|
###-#### tom sheer wall Shear OK. 8/23/2001 1:58:50 PM
|
BLD-Framing/Rough-in | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Jim Sly
|
|
|
nailing insp -tom ###-#### Roof nailing OK....Checked wall nailing....Verbal corr More nails needed and Eng to verify nailing at (triangle) 6. 8/20/2001 10:09:46 AM
|
BLD-Conference | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Jim Sly
|
|
|
###-#### Shear South wall Stinker.....OK. 8/10/2001 8:36:17 AM
|
BLD-Conference | 7/10/2001 | 7/13/2001 | 7/13/2001 | P | PART |
Jim Sly
|
|
|
chuck ###-#### around 1:15 as per jim sly Pre Const Conf. 7/13/2001 3:59:27 PM
|
BLD-Final | 6/20/2001 | 6/21/2001 | 6/21/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### SHOULD BE FOUND INSP.....FOUND APPEARS OK..... PEND SPECIAL INP AND APPR (conc PSI) 6/21/2001 2:22:41 PM
|
BLD-Footing | 6/14/2001 | 6/15/2001 | 6/15/2001 | P | PART |
Jim Sly
|
|
|
###-####
|
(F) Reprint permit | | | 4/2/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/30/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/30/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/31/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/31/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/31/2001 | | DONE |
|
|
|
Linda ajusted fees
|
Plan assigned to (MLO) | 10/12/1999 | 10/12/1999 | 1/30/2001 | | PASS |
Mike Otto
|
|
|
1/30/2001 14:48:56 MLO - activity updated through activity BLDA022 from case BLD99-03062.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2001 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/11/2000 | | 1/26/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/25/2001 | | DONE |
|
|
|
Received two copies of revised sheet ES1.0 from Rick Toews, routed to Mike Otto. KMM
|
CHANGE STATUS TO (PND) | | | 10/17/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 10/6/2000 | | DONE |
|
|
|
RECEIVED LETTER FROM RICK TOEWS ASKING FOR A TIME EXTENSION FOR THIS PROJECT'S BUILDING PERMIT. ROUTED TO MIKE O AND TIM H. KMM
|
Routing - PUBLIC WORKS | 6/9/2000 | | 6/9/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION. 6/7/00 DAR
|
Routing - PUBLIC WORKS | 6/2/2000 | | 6/2/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION PER BRIAN MURPHY. 6/2/00
|
Routing - PUBLIC WORKS | 3/10/2000 | | 3/13/2000 | | FAIL |
|
|
|
REQUIRES SUB. APPROVAL. KMM
|
Routing - PLAN CHECK | 3/8/2000 | | 3/10/2000 | | PASS |
|
|
|
3/10/00 - PUBLIC WORKS HAS STILL NOT APPROVED THIS PROJECT DUE TO AN ILLEGAL LAND DIVISION. MLO
|
Plan resubmittals received | | | 3/7/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM BRS ARCHITECTS, THE SHEETS ARE ON THE KYSOR PANEL SYSTEMS, 2 SHEETS OFA-1, FORWARDED SAME TO MIKE OTTO. 3/7/00 DAR
|
Plan resubmittals received | | | 3/3/2000 | | FAIL |
|
|
|
RECEIVED REVISED PLAN SHEET A-1 OF 1 HOWEVER THEY WERE NOT STAMPED OR SIGNED. CONTACTED TICK TOEWS OF THIS NEED. KMM
|
Plan Reviewer's activity | | | 2/3/2000 | | PEND |
|
|
|
mailed and faxed letter accepting cooler panels with conditions to manufacture and architect. MLO
|
Routing Off Site - STRUCTURAL | 12/3/1999 | | 12/7/1999 | | PASS |
|
|
|
SENT PLAN RESUBMITTALS TO CONSULTING ENGINEER VIA PDQ. 12/3/99
12/7/99 RECEIVED COPY OF REVIES LETTER AND PLANS BACK FROM OUTSIDE ENG. ROUTED TO MIKE OTTO. KMM
|
Plan resubmittals received | | | 12/6/1999 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS, SHEETS S4 & A 15, FROM RICK TOEWS, BRS ARCHITECTS, FORWARDED SAME TO MIKE OTTO. 12/6/99 DAR
|
Routing - PLAN CHECK | 12/6/1999 | | 12/6/1999 | | FAIL |
|
|
|
item number 23 on the corrections from 11-23-99 had no response. MLO
|
Plan resubmittals requested | | | 12/6/1999 | | FAIL |
|
|
|
architect contacted regarding lack of response to item number 23 on correction list of 11-23-1999. MLO
|
Plan resubmittals received | | | 12/2/1999 | | PEND |
|
|
|
received structural resubs.
|
Routing - PLAN CHECK | 11/22/1999 | | 11/23/1999 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 11/23/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT ON RESUBMITTAL. MLO
|
Plan resubmittals received | | | 11/22/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS TI, A1, A9, A15, ONE PLAN CHANGE BULLETIN. ROUTED TO MIKE OTTO. KMM
|
Routing - FIRE | 11/17/1999 | 11/18/1999 | 11/18/1999 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 11/18/1999 | | FAIL |
|
|
|
structural corrections mailed and faxed to architect. MLO
|
Routing Off Site - STRUCTURAL | 11/3/1999 | | 11/18/1999 | | FAIL |
|
|
|
SENT SET OF PLANS TO CONSULTANTING STRUCTURAL ENGINEER VIA PDQ. 11/3/99 DAR
|
Plan Review Completed(1st rev) | | | 11/18/1999 | | PEND |
|
|
|
|
Routing - PLUMBING | 11/5/1999 | | 11/16/1999 | | PASS |
|
|
|
Plans sent back to plan check - use boise city approved grease interceptor design, attached, additional cross connection protection may be required, waste lines longer than 5' must have full sized c.o.
|
Routing - PLAN CHECK | 11/2/1999 | | 11/4/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Plan resubmittals received | | | 11/2/1999 | | PEND |
|
|
|
Received plan complete resubmittals from BRS Architects, forwarded same to Mike Otto. 11/2/99 DAR
|
Plan resubmittals received | | | 11/1/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS (FULL SETS) FROM BRS, FORWARDED SAME TO MIKE OTTO. 11/1/99 DAR
|
Routing - PLANNING | 10/21/1999 | | 11/1/1999 | | PASS |
|
|
|
Conditional Use comments (SAR): Landscape buffer must be 20' wide abutting Chinden.
Design Review comments (MGS): approved per DRH99-0121 and revised plans in file.
|
Routing - PLAN CHECK | 10/22/1999 | | 10/22/1999 | | HOLD |
|
|
|
RECEIVED LETTER FROM ARCHITECT TO HOLD REVIEW PROCESS NEW PLANS ARE BEING PREPARED FOR SUBMITTAL. 10-22-99 -MLO
|
Routing - PUBLIC WORKS | 10/19/1999 | 10/19/1999 | 10/21/1999 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION. PER JIM RICH. 10/21/99 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 10/20/1999 | | DONE |
|
|
|
RECEIVED STAMPED AND SIGNED MECH AND HOOD SHEETS. KMM
|
Plan resubmittals received | | | 10/20/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF STAMPED AND SIGNED M-1 THRU M-5, H-1 THRU H-3 WITH SP6 & SP7 PUT WITH PLANS. KMM
|
Plan resubmittals received | | | 10/19/1999 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS P-1, P-3, P-5, P-8, AND P-4. CHUCK MELLEN PLACED INTO REVIEW SETS. KMM
|
Plan routing begun/NEW & ADDTN | | | 10/19/1999 | | |
|
|
|
|
Routing Off Site - C.D.H | 10/12/1999 | 10/12/1999 | 10/18/1999 | | PASS |
|
|
|
CHUCK MELLEN TOOK PLANS OUT TO CDH. KMM
|
Plan Review Report | | | 10/14/1999 | | DONE |
|
|
|
LINDA THIS PROJECT WAS SUBMITTED UNDER ONE PERMIT, BLD99-03062. IT WILL BE SEPARATED INTO FOUR DIFFERENT PERMITS. THE INITIAL VALUE FOR ALL FOUR WAS $754,280.00. THE NEW VALUES ARE. 1. GRADING AND DRAINAGE $190,450 2.CONVENINCE STORE BUILDING $170,555 3. JACK-IN-THE BOX T.I. $180,555 4. GAS ISLAND CANOPY $39,800 KMM
|
Case Summary (BLD) | | | 10/12/1999 | | DONE |
|
|
|
|
Application received | | | 10/11/1999 | | |
|
|
|
|
Pending Assignment by MYS | 10/11/1999 | | | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | | | FAIL |
|
|
|
PLANS REQUIRE (SEPARATE PERMITS FOR) 1. CANOPY, WHICH REQUIRES THREE COPIES OF MAUFACTURES ENG. PLANS, AND CERT. OF VALUE.
2. STORE REQUIRES SEPARATE PERMIT. I WILL USE THIS BLD# FOR THE STORE. CANOPY REQUIRES SEPARATE PERMIT. JACK IN THE BOX REQUIRES A SEPARATE PERMIT. RECEIVED CERT. OF VALUES 10/14/99
THERE WILL BE A TOTAL OF FOUR PERMITS FOR THIS PROJECT.
MECH. PLANS NEED TO BE STAMPED AND SIGNED.
HOOD SHEETS NEED TO BE STAMPED AND SIGNED.
APPLICANT WILL BE APPLING FOR SEPARATE GRADING AND DRAINAGE PERMIT ON SEPARATE PLANS. KMM
10/18/99 RECEIVED PLANS BACK FROM CDH. STILL REQUIRE
1. MECH. PLANS AND HOOD PLANS TO BE STAMPED AND SIGNED
|
Extend Permit 180 days | | | | | |
|
|
|
REQUEST RECEIVED TO EXTEND APPLICATION FOR PERMIT FOR 180 DAYS DUE TO PROBLEMS WITH GAINING APPROVAL FOR NEW SUBDIVISION. 4-5-2000. LETTER FORWARDED TO T. HOGALND FOR REVIEW. MLO
|