BLD-Framing/Rough-in | 12/10/1999 | 12/13/1999 | 12/13/1999 | P | PART |
Carl Dependahl
|
|
|
for grid ins--gary ###-####
|
BLD-Framing/Rough-in | 12/6/1999 | 12/7/1999 | 12/7/1999 | A | PART |
Carl Dependahl
|
|
|
STERLING DANIELS ###-#### RE-INSP R/I C/N ok; need clg. Insp.
|
BLD-Framing/Rough-in | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | FAIL |
Carl Dependahl
|
|
|
GARY ###-#### C/N re: non-treated lumber @ II-N.
|
Issue PAID IN FULL permit | | | 11/18/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/17/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/17/1999 | | DONE |
|
|
|
called Jim left message ###-####
|
Case Summary (BLD) | | | 11/16/1999 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/1999 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 10/19/1999 | | 11/15/1999 | | PASS |
|
|
|
11/15/1999 08:25:47 RMH - activity updated through activity BLDA022 from case BLD99-03133.
|
Plan resubmittals received | | | 11/12/1999 | | FAIL |
Ron Hill
|
|
|
FAXED REQUIREMENTS TO THE PROJECT MANAGER PATRIC LAHEY
|
Plan resubmittals received | | | 11/12/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HUMMEL ARCHITECTS, JIM OTRADOSKY, FORWARDED SAME TO RON HILL. 11/12/99 DAR
|
Routing - FIRE | 11/9/1999 | | 11/10/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/20/1999 | | 11/8/1999 | | FAIL |
Ron Hill
|
|
|
Faxed requirements to the architect, will route to fire department.
|
Routing - PUBLIC WORKS | 10/19/1999 | | 10/20/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 10/19/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Application received | | | 10/15/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/15/1999 | | PEND |
|
|
|
PLANS NOT FULLY DIMENSIONED. KMM
|
Received Certificate of Value | | | 10/15/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/10/1999 | 11/10/1999 | | | PEND |
|
|
|
|