Permit Information
Permit NumberBLD99-03287
StatusFinaled
Name S-SIXTEEN LIMITED PARTNERSHIP
Site Address 405 S 8TH ST
Project Name8TH ST MARKETPLACE
Customer Number 
ePlanReviewNo
Description
Remodeling an existing unoccupied space into storage use on the south side of the basement per approved plans on file. Work to include relocating and constructing a new one-hour fire rated corridor with new rated doors, fire/smoke dampers at duct openings in new rated corridor, new exit stairways on west side, interior walls with doors, interior finish, fire sprinkler work, some mechanical work, some plumbing work, and some electrical work. NOTE: This building is fully fire sprinklered for 1-hr. substitution. (P.C.#870-99) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  12/22/2008  
Fee Review-notes6/12/20036/12/20036/12/2003 DONE
Fee Review-notes10/29/199910/29/19992/20/2001 DONE
additional value from sub.
Permanent occupancy  9/11/2000 DONE
Perm. Occ. Cert. #8366 issued 9-11-00 to S-Sixteen dba 8th Street Marketplace.
Permanent Occupancy 9/1/20009/1/2000 DONE
Details
BLD-Final8/31/20009/1/20009/1/2000PPASS
Details
skip ###-#### fn signed by 409 ok by me 9/1/2000 4:09:29 PM
FIRE-Final Inspection8/31/20009/1/20009/1/2000PPASS
DetailsRick Jackson
skip ###-#### fire fn signed for structural inspector also per Perry 9/1/2000 2:05:01 PM
FIRE-Final Inspection8/29/20008/30/20008/30/2000PNR
DetailsRick Jackson
Scheduled by Inspector: 409 On 8/29/2000 will reschedule 8/31/2000 7:59:11 AM
BLD-Final8/28/20008/29/20008/29/2000PPASS
Details
Skip Jones ###-#### signed for me by 409 9/1/2000 4:08:53 PM
FIRE-Final Inspection8/28/20008/29/20008/29/2000PNR
DetailsRick Jackson
Skip Jones ###-#### rescheduled for 8/30 8/29/2000 12:10:42 PM
BLD-Final8/3/20008/4/20008/4/2000ACANC
Details
###-#### nr 8/4/2000 4:04:55 PM
FIRE-Final Inspection8/3/20008/4/20008/4/2000ANR
DetailsRick Jackson
###-#### talked to Skip via telephone and he said he wouldn't be ready to test the alarms until next week. 8/4/2000 10:47:26 AM
BLD-Conference7/19/20007/20/20007/20/2000APART
Details
Skip ###-#### walked through for pre signoff 7/21/2000 9:07:03 AM
BLD-Conference7/12/20007/13/20007/13/2000AFAIL
Details
skip ###-#### no response from contr. 7/14/2000 4:41:56 PM
BLD-Framing/Rough-in4/17/20004/17/20004/17/2000PPART
Details
###-#### ok to cover hall ceiling 04/17/2000
BLD-Conference3/27/20003/28/20003/30/2000APART
Details
Skip ###-#### on the basement corridor level landing not required on inside of storage units 03/30/2000
FIRE-Conference3/27/20003/28/20003/28/2000APART
DetailsRick Jackson
Skip ###-#### Reviewed project with contractor (skip). 3/30/00 10:47:12 AM
Telephone call  12/20/1999 DONE
called Margie Kennedy at ###-#### left message on voice mail
Print Occupancy Form  12/20/1999 DONE
Inspection Record Card- Bld  12/20/1999 DONE
Routing - PLAN CHECK12/9/199912/9/199912/18/1999 PASS
Plans approved and taken to front desk.
Plan assigned to (JCB)11/8/1999 12/18/1999 PASS
DetailsJason Blais
PLANS/APPL TAKEN TO FRONT DESK  12/18/1999  
Plan resubmittals received  12/17/1999 DONE
PLAN RESUBMITTALS RECIVED FROM ARMSTRONG ARCHITECTS, SHEET A1.0 , FORWARDED SAME TO JASON BLAIS. 12/17/99 DAR
Routing - FIRE12/8/199912/9/199912/9/1999 PASS
Plan Review Completed(1st rev)  12/9/1999 PEND
Plan resubmittals requested  12/8/1999 PEND
Resubmittal drawings and response required for further review.
Routing - PLAN CHECK11/8/1999 12/8/1999 FAIL
Plan review report sent and faxed to architect. Resubmittal drawings and response required for further review. Plans routed to fire dept.
Pending Assignment by MYS11/8/1999 11/8/1999 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  11/8/1999 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Routing - PUBLIC WORKS11/8/1999 11/8/1999 PASS
Additional plans submitted  11/4/1999 PEND
RECEIVED PLANS MEETING SUBMITAL REQUIREMENTS FROM ARMSTRONG ARCHITECTS. PROCESSED PLANS AND FORWARDED THEM TO MARLENE FOR SCREENING. 11/4/99 DAR
Application received  10/29/1999  
Recd Pcfee & Taken To Pln CK     
Issue PAID IN FULL permit