Letter of compliance | | | 10/16/2000 | | DONE |
|
|
|
Letter of Compliaince #19953 issued 10-16-00.
|
FIRE-Final Inspection | 10/11/2000 | 10/12/2000 | 10/12/2000 | A | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 10/6/2000 | 10/6/2000 | 10/6/2000 | P | PASS |
Tom Arcoraci
|
|
|
chip ###-#### ok for letter of comp after fire insp passes alarm system 10/6/2000 4:17:56 PM
|
BLD-Grading Inspection | | | 10/6/2000 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete according to the approved plan. $1000.00 bond is required to complete drainage and fine grading.
|
BLD-Conference | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | PART |
Tom Arcoraci
|
|
|
chip ###-#### 10/5/2000 1:58:54 PM occ sep in garage conf 10/5/2000 2:31:53 PM
|
BLD-Framing/Rough-in | 5/31/2000 | 6/1/2000 | 6/1/2000 | A | PASS |
Tom Arcoraci
|
|
|
Rick ###-#### E/C ok 6/1/00 2:34:05 PM
|
BLD-Framing/Rough-in | 5/24/2000 | 5/25/2000 | 5/25/2000 | P | FAIL |
Russ Owen
|
|
|
###-#### C/N posted 5/31/00 9:13:37 AM
|
BLD-Framing/Rough-in | 5/12/2000 | 5/15/2000 | 5/15/2000 | A | PART |
Russ Owen
|
|
|
nailing \\###-#### as late as possible ok to side, upon approval from engineer. 5/15/00 2:58:32 PM
|
BLD-Framing/Rough-in | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | FAIL |
Russ Owen
|
|
|
sheer nailing Chip ###-####. C/N posted
|
BLD-Framing/Rough-in | 4/26/2000 | 4/26/2000 | 4/26/2000 | P | PART |
|
|
|
###-#### MADE OK FOR THE SHEAQRNAILLING ONLY 5/1/00 7:46:28 AM
|
BLD-Framing/Rough-in | 4/24/2000 | 4/25/2000 | 4/25/2000 | A | FAIL |
Carl Dependahl
|
|
|
shear nail chip ###-#### No approved plans 4/26/00 11:54:15 AM
|
BLD-Framing/Rough-in | 4/21/2000 | 4/24/2000 | 4/24/2000 | P | CANC |
Tom Arcoraci
|
|
|
###-####\\nailing
|
BLD-Footing | 3/8/2000 | 3/8/2000 | 3/7/2000 | P | PASS |
Wes Worcester
|
|
|
###-#### Planter & stair case ftgs. occ. 3/9/00 11:25:28 AM
|
BLD-Foundation | 2/14/2000 | 2/14/2000 | 2/14/2000 | P | PART |
Carl Dependahl
|
|
|
Ret. wall, int. ftg. wall.
|
BLD-Footing | 2/3/2000 | 2/4/2000 | 2/4/2000 | A | PART |
Jim Storey
|
|
|
J Jones ###-#### Exterior ft. & rebar ok interior N/R archived excavation report from Reh. Reed. 2/4/00 2:04:25 PM
|
Issue PAID IN FULL permit | | | 1/27/2000 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 12/1/1999 | 12/1/1999 | 12/1/1999 | | PASS |
Dan Overy
|
|
|
12/1/99 10:59:41 DJO - activity updated through activity BLDA022 from case BLD99-03288.
|
Plans ACCEPTED BY PLAN CHECK | | | 12/1/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/1/1999 | | DONE |
|
|
|
|
Telephone call | | | 12/1/1999 | | DONE |
|
|
|
called permit ready and fees due Philip Rietze applicant. He will call Merit Homes.
|
Routing - PLANNING | 11/10/1999 | 11/10/1999 | 11/12/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/29/1999 | 10/29/1999 | 11/10/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 10/29/1999 | 10/29/1999 | 11/9/1999 | | PASS |
Rita DeYoung
|
|
|
Driveway is steeper than 8% that is indicated on plan. Called Phil Rietz and asked him to look at it and get back to me.
Phil Rietze raised bottom of ramp to make grade down centerline of driveway 11%.
|
Application received | | | 10/29/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 11/12/1999 | 11/12/1999 | | | PEND |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Pending Assignment by DJO | 10/29/1999 | | | | PEND |
Dan Overy
|
|
|
|