Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-03377
StatusFinaled
Name SMOKY MTN PIZZA
Site Address 7609 W OVERLAND RD Unit: 150
Project NameBOISE SPECTRUM
Customer Number 
ePlanReviewNo
Description
New tenant in an existing 2,232 sq.ft. tenant space for use as an assembly occupancy (A-3) restaurant/dining and (B) occupancy kitchen/service area per approved plans on file. Work to include demolition of several components from previous tenant, new interior walls, soffit/bulkhead construction, interior finish, some suspended ceiling areas, kitchen modifications, new Type II Hood installation, new walk-in cooler, mechanical, plumbing, and electrical work. NOTE: This building is fully fire sprinklered for 1-hr. fire resistive substitution. This space formerly occupied by the Studio Collection. (P.C.#889-99) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes11/10/1999 3/30/2000 DONE
Permanent occupancy UNPAID FEE  1/25/2000 DONE
Perm. Occ. Cert. #8107 issued 1-25-00 to the Smoky Mountain Pizza Restaurant.
Permanent Occupancy 1/7/20001/7/2000 DONE
Details
BLD-Final1/6/20001/7/20001/7/2000APASS
DetailsCarl Dependahl
Struct. ok for C/O.. if CDHD permanent.
Temporary occupancy  1/6/2000 PART
Temp. Occ. Cert. #3965 issued 1-6-00 to Smoky Mountain Pizza.
FIRE-Final Inspection1/4/20001/5/20001/5/2000APASS
DetailsJoe Tawney
###-####-- JERRY FN FIRE. Reinsp. ok for perm. occ.
BLD-Final1/4/20001/5/20001/5/2000PPART
DetailsCarl Dependahl
JERRY ###-#### FN OCC. Ok for T/O; need health, card to owner.
FIRE-Final Inspection1/3/20001/4/20001/4/2000AFAIL
DetailsJoe Tawney
jerry ###-####. Final fail C/N issued.
BLD-Framing/Rough-in12/28/199912/29/199912/29/1999AFAIL
DetailsWes Worcester
Scheduled by a contractor via Hello! on 12/28/1999 at 15:26:39. Contact: ###-####. Ok to cover rear of partial wall only- remainder of C/N not done.
FIRE-Sprinkler Rough-in12/23/199912/27/199912/27/1999AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/23/1999 at 12:52:32. Contact: . Painted head at main entrance; walk-in cover not sprinklered; ok to cover hard lid areas.
BLD-Framing/Rough-in12/22/199912/23/199912/23/1999PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/22/1999 at 14:40:05. Contact: . Ok to cover ceiling area; Add bracing @ wall etc., C/N.
BLD-Framing/Rough-in12/22/199912/22/199912/22/1999PFAIL
DetailsCarl Dependahl
###-#### Jerry Todd Need elec. R/I & accessible counter area recall.
Routing - PLAN CHECK12/21/199912/21/199912/22/1999 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  12/22/1999  
Inspection Record Card- Bld  12/22/1999 DONE
Print Occupancy Form  12/22/1999 DONE
Issue PAID IN FULL permit  12/22/1999 DONE
Plan assigned to (JCB)11/17/1999 12/22/1999 PASS
DetailsJason Blais
Routing - FIRE12/16/199912/20/199912/20/1999 PASS
Plan resubmittals received  12/20/1999 DONE
RECEIVED PLAN RESUBMITTALS FROM MARK KNOWLES, SHEETS A.O,A.1,A.2,A.3, FORWARDED SAME TO JASON BLAISE. 12/20/99 DAR
Plan Review Completed(1st rev)  12/20/1999  
Plan resubmittals requested  12/16/1999 PEND
Plan resubmittals and response required for further review.
Routing - PLAN CHECK11/24/1999 12/16/1999 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to fire dept.
Additional plans submitted  12/6/1999 DONE
RECEIVED ADDITIONAL PLANS FROM JERRY TODD , THE PLANS WERE ENGINEERING BY DEVCO ENGINEERING INC. PLANS ATTACHED TO CIRCULATING PLANS . 12/06/99
Routing - PLUMBING11/18/1999 11/24/1999 PASS
Plan Reviewer's activity  11/18/1999 DONE
Issued an interior demolition permit BLD99-03445.
Routing - PUBLIC WORKS11/18/1999 11/18/1999 PASS
Pending Assignment by MYS11/17/1999 11/17/1999 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  11/17/1999 DONE
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  11/15/1999  
Application received  11/10/1999  
Recd Pcfee & Taken To Pln CK  11/10/1999 DONE