Case Summary (BLD) | | | 12/21/2007 | | |
|
|
|
|
Letter of compliance | | | 3/25/2002 | | DONE |
|
|
|
Letter of Compliance #22313 issued 3-25-02.
|
BLD-Conference | 3/21/2002 | 3/21/2002 | 3/21/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 3/21/2002 9:49:49 AM rec'd Final Mti report verifying proper adhesion of fireproofing, c/n ok. 3/21/2002 10:14:03 AM
|
BLD-Final | 3/21/2002 | 3/21/2002 | 3/21/2002 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 3/21/2002 10:06:49 AM c/n ok...ok for perm l/c only. 3/21/2002 11:18:23 AM
|
BLD-Final | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 3/21/2002 10:15:08 AM ok for l/c 3/21/2002 2:09:07 PM
|
FIRE-Final Inspection | 3/21/2002 | 3/21/2002 | 3/21/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/21/2002 3:03:08 PM
|
BLD-Final | 3/8/2002 | 3/11/2002 | 3/11/2002 | A | FAIL |
Carl Dependahl
|
|
|
mel ###-#### fn occ ; verify fireproofing approval re MTI affidavit, reports 375 &386. rec'd statement of repair from ISI (Kip Frawley, spray-on mgr.) but no approval or acknowledgement from arch.3/11/2002 4:03:12 PM 3/11/2002 4:06:22 PM
|
Override - Parcel Holds | | | 3/8/2002 | | |
|
|
|
|
Override - Parcel Holds | | | 3/8/2002 | | |
|
|
|
|
(F) Reprint permit | | | 2/14/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/12/2002 | | DONE |
|
|
|
|
Fee Review-notes | 5/2/2000 | 5/2/2000 | 1/14/2002 | | DONE |
|
|
|
final certs.
|
BLD-Final | 1/2/2002 | 1/2/2002 | 1/2/2002 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/2/2002 3:20:31 PM c/n, need eng'rs complete response to spec insp items, permanent oks from all agencys, previous corrections completed, etc . ok for t/o only per P&Z (Tempra)
|
Temporary occupancy | | | 1/2/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4697 issued 1-2-02 to the Ada County Courthouse shell and core.
|
BLD-Final | 12/28/2001 | 12/31/2001 | 12/31/2001 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/28/2001 at 17:41:37. Contact: ###-####...keep c/n. 12/31/2001 5:49:23 PM
|
FIRE-Final Inspection | 12/27/2001 | 12/28/2001 | 12/28/2001 | P | FAIL |
Rick Jackson
|
|
|
###-#### door hardware; closures; with Carl D and Lee 12/28/2001 4:52:50 PM
|
Code Occupancy Approval | | | 12/19/2001 | | PASS |
|
|
|
|
BLD-Conference | 12/12/2001 | 12/12/2001 | 12/12/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/12/2001 6:04:02 PM need eng's, arch's, & spec insp reports
|
BLD-Conference | 11/29/2001 | 11/29/2001 | 11/29/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/29/2001 2:27:21 PM ok to delete 1hr const at north wall except at & above sally port closer than 39' to P.L. per waiver request approved by T. Hogland.
|
BLD-Energy code compliance | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | NR |
Carl Dependahl
|
|
|
LORA ###-####; need arch's approval /letter to delete 1hr const at north wall. will submit 11/27/2001 1:48:52 PM
|
BLD-Framing/Rough-in | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/27/2001 1:47:41 PM bsmt: c/n re corridor penetrations, lg. panel box at elec. rm... grid wires, pods;labels at rated doors & glass. repair spray-on F.P. at beams, pan over garage, etc. Verify fire-smoke dampers at hvac at elev lobbies/corridor. ok to tile 2hr exit pass. at 1st fl, grid ok.
|
BLD-Conference | 11/26/2001 | 11/26/2001 | 11/26/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/26/2001 11:23:41 AM w/ George Eidam, Eidam eng's...need standby power for one elevator to 5th floor per UBC 1104; 4th floor ok per exception.
|
Override - Parcel Holds | | | 11/26/2001 | | DONE |
Darla L Downs
|
|
|
Parcel Tag Notes: Prior to issuance of a final occupancy permit the parking structure to the east shall be completed. Per Tempra K. Wilson X3836. Reason for OverRide: THIS IS FOR AN ENERGY CODE INSPECTION ///DLD
|
BLD-Conference | 11/16/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/16/2001 11:08:44 AM w/ 409 re ADA req't for standby power to 1 elevator, per UBC1104.1.3...will advise bldr.
|
BLD-Conference | 11/8/2001 | 11/8/2001 | 11/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/8/2001 10:11:26 AM rec'd, reviewed insp reports...soils at west side entry retest ok per mti
|
BLD-Conference | 9/20/2001 | 9/20/2001 | 9/20/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/20/2001 6:01:57 PM need repair fireproofing at" new" add'l beams...verbal c/n.
|
BLD-Framing/Rough-in | 9/5/2001 | 9/5/2001 | 9/5/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/5/2001 3:42:07 PM need recheck spray on fire proofing removed at col's /spandrels & secondary floor supports attached after-the-fact...MTI report req'd.
|
BLD-Conference | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 8/21/2001 9:48:11 AM mel ###-#### shell...need all reports 8/21/2001 4:38:23 PM
|
BLD-Conference | 6/14/2001 | 6/14/2001 | 6/14/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/14/2001 3:21:02 PM data boxes at floor, wip ok
|
BLD-Framing/Rough-in | 6/7/2001 | 6/7/2001 | 6/7/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/7/2001 4:39:19 PM ext gfrc panels
|
BLD-Framing/Rough-in | 5/31/2001 | 5/31/2001 | 5/31/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/31/2001 3:33:20 PM with Mel P... keep c/n, install shaft for hvac at NE corner area, fl 3-5...
|
BLD-Framing/Rough-in | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/16/2001 5:12:55 PM keep c/n re shafts, 4hr & 2hr occ separations.
|
BLD-Framing/Rough-in | 5/11/2001 | 5/11/2001 | 5/11/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/11/2001 4:17:01 PM need shafts at hvac exhaust thru floors 3,4; clarify masonry const for 4hr wall at bsmt...cl. B-4 blocks req'd?
|
BLD-Framing/Rough-in | 5/3/2001 | 5/3/2001 | 5/3/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/3/2001 4:52:54 PM curtain wall firestops at fls.2,3,4,5 appear ok...mti also inspecting
|
BLD-Framing/Rough-in | 4/30/2001 | 4/30/2001 | 4/30/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/30/2001 5:00:36 PM firestops at 3rd fl curtain wall/floor...ok; has mti insp. too.
|
BLD-Framing/Rough-in | 4/13/2001 | 4/13/2001 | 4/13/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/13/2001 2:01:03 PM 2nd fl curtain wall firestops...wip
|
BLD-Framing/Rough-in | 4/12/2001 | 4/12/2001 | 4/12/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/12/2001 10:50:31 AM continuing insp...firestops 2nd fl east side...rework gaps, holes. wip
|
BLD-Framing/Rough-in | 4/11/2001 | 4/11/2001 | 4/11/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/11/2001 5:44:30 PM 2nd fl curtain wall firestops at north & east sides ok per detail; wip for shafts, & corridor walls
|
BLD-Conference | 4/9/2001 | 4/9/2001 | 4/9/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/9/2001 10:02:48 AM w/ Mel Perez, supt. re floor/curtainwall firestop assy 4/9/2001 10:03:20 AM
|
BLD-Conference | 2/27/2001 | 2/27/2001 | 2/27/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/27/2001 5:58:11 PM faxed floor detail for penetrations
|
BLD-Conference | 2/21/2001 | 2/21/2001 | 2/21/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/21/2001 4:07:37 PM w/ Laura Patten re 2hr fl assy...eng'd judgement to be provided for protection of boxes
|
BLD-Conference | 2/8/2001 | 2/8/2001 | 2/8/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/8/2001 4:25:07 PM gave list of questions for clarification to proj. eng'r re floor penetrations
|
BLD-Conference | 2/5/2001 | 2/5/2001 | 2/5/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/5/2001 12:04:55 PM w/ proj engr; resub. re boxes
|
BLD-Conference | 2/1/2001 | 2/1/2001 | 2/1/2001 | P | PASS |
Carl Dependahl
|
|
|
Laura Patton ###-####; rec'd resub for floor boxes, will advise..discussed handrails w/ supt. 2/2/2001 12:01:02 PM
|
BLD-Conference | 2/1/2001 | 2/1/2001 | 2/1/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/1/2001 4:53:27 PM w/Laura re fl boxes
|
BLD-Conference | 1/11/2001 | 1/11/2001 | 1/11/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/11/2001 5:13:50 PM walk thru
|
BLD-Conference | 1/9/2001 | 1/9/2001 | 1/9/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/9/2001 6:10:07 PM w/ super, proj engr at sitr. need submittal for floor boxes
|
Plan resubmittals received | | | 11/7/2000 | | DONE |
|
|
|
RECEIVED ONE COPY OF REVISED STRUCTURAL SHEETS S01, S201, S202, S211, S212. S213, S214, S215, S221, S222, S223, S224, S231, S232, S233, S234, S241, S242, S243, S244, S251, S252, S253, S254, S261, S262, S270, S31, S51, S52, S53, S55, S71, S54, S72, S73, S74, S75, S76, S77, S78, S79 . Routed to Jim Storey KMM
|
(F) Reprint permit | | | 5/2/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/1/2000 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 11/16/1999 | 11/16/1999 | 4/26/2000 | | PASS |
John Menard
|
|
|
4/26/00 11:50:14 JCM - activity updated through activity BLDA022 from case BLD99-03383.
|
Routing - PLAN CHECK | 4/19/2000 | | 4/26/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2000 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/26/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/26/2000 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/21/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM LAURA PATTEN, TWO SETS OF SHEETSA024,211,213,214,215, A420AND A LETTER FROM LOMBARD CONRAD ARCHITECTS. 4/21/00 DAR
|
Routing - PUBLIC WORKS | 4/18/2000 | | 4/19/2000 | | DONE |
|
|
|
|
Routing - PLUMBING | 4/17/2000 | | 4/18/2000 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/17/2000 | | PEND |
|
|
|
FAXED LAURA PATTEN A COPY OF THE COMMENT LIST THAT I MAILED TO HER ON 4/14/00.
|
Routing - PLAN CHECK | 4/5/2000 | | 4/17/2000 | | |
|
|
|
|
Plan resubmittals requested | | | 4/14/2000 | | PEND |
|
|
|
MAILED LAURA PATTEN A LETTER REQUESTING ADDITIONAL REVISIONS.
|
Routing - PUBLIC WORKS | 2/29/2000 | | 4/5/2000 | | FAIL |
|
|
|
NEED REVISIONS OF MECHANICAL PLAN SHEETS THAT SHOW THE GEOTHERMAL HEAT EXCHANGERS RELOCATED FROM THE CHILLER ROOM TO THE ROOM ON THE WEST WALL OF THE BASEMENT ,PER DAVE LOGAN. - THIS IS NEW LOCATION OF HEAT EXCHANGER. 3/3/00 DAR
|
Routing - PLUMBING | 3/23/2000 | | 4/5/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/3/2000 | | 3/23/2000 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 3/23/2000 | | PEND |
|
|
|
Mailed Laura Patten at Morrison Knudsen a letter requesting additional revisions.
|
Routing Off Site - STRUCTURAL | 2/24/2000 | | 3/1/2000 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE RESUBMITTED S-DRAWINGS 2/22/2000 TO OUTSIDE ENG. KMM RECEIVED APPROVAL LETTER FROM CONSULTING ENGINEER. JCM
|
Routing - PLAN CHECK | 1/10/2000 | | 2/29/2000 | | |
|
|
|
|
Plan resubmittals received | | | 2/25/2000 | | DONE |
|
|
|
RECEIVED THE OTHER COPY OF REVISED S SHEETS. ROUTED TO JOHN M. KMM
|
Plan resubmittals received | | | 2/24/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED S DRAWINGS. REQUESTING ONE MORE COPY. ONE COPY WILL GO TO OUTSIDE ENG. 2/24/2000. I WILL ROUTE THE OTHER COPY TO JOHN. I CONTACTED LAURA ABOUT THE ADDITIONAL COPY. SHE STATED IT WILL BE HERE THIS AFTERNOON. RECEIVED TWO COPIES OF REVISED STRUCTURAL CALCS. WITH RESPONSES. ROUTED TO JOHN M. KMM
|
Routing - FIRE | 12/22/1999 | 1/7/2000 | 1/7/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/7/2000 | | PEND |
|
|
|
|
Telephone call | | | 12/22/1999 | | DONE |
|
|
|
CONTACTED ROBERT PRYOR CONCERNING REQUIRMENTS FOR A GRADING AND DRAINAGE PERMIT AS WELL AS A BLD. FOUNDATION PERMIT. FAXED ABOVE REQUIRED INFORMATION. KMM
|
Plan resubmittals requested | | | 12/22/1999 | | PEND |
|
|
|
MAILED SCOTT HENSON AT LOMBARD-CONRAD A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Routing - PLAN CHECK | 12/3/1999 | | 12/22/1999 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/16/1999 | | 12/3/1999 | | FAIL |
|
|
|
SENT PLANS, SPECIFICATIONS, SOILS REPORT AND ENGINEERING CACULATIONS TO CONSULTING ENGINEER VIA PDQ. 11/16/99 DAR
12-3-99 RECEIVED REVIEW LETTER FROM OUTSIDE ENG. ROUTED TO JOHN M. KMM
|
Plan resubmittals requested | | | 12/3/1999 | | PEND |
|
|
|
FAXED SCOTT HENSON AT LOMBARD-CONRAD A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing - PLANNING | 11/29/1999 | | 12/2/1999 | | PASS |
|
|
|
Routed to Mike Hall. Per CUP98-81: Site plan does not comply with required 10' setback on west end of parking lot (NW corner); see condition 1(a) of DR99-60. Okay to pass but required changes are redlined. Revised sheets A110 and A120 are needed for plan set. Applicant must submit a revised site plan and meet with planning and DR staff for approval of parking lot modification, since significant changes to parking lot are required. Also, phasing is different than approved cup but perhaps does comply with DR approval. Per condition 3 of DR99-60, a revised phasing plan must be submitted to comply with the CUP. The phasing proposed in the building plans is okay and does comply with parking requirements (according to cup, 527 spaces are estimated to be required for courthouse and other uses within phase 1). Compliance with CUP condition #7 will be determined on later permit application of phase 1 - determination not necessary for this shell and core permit. ** Routed to Tempra Wilson.
Final landscape plan still needs to be approved by Design Review staff. Discussed with Eric Jensen who will be submitting a timeline.
|
Routing - PLUMBING | 11/18/1999 | | 11/29/1999 | | FAIL |
|
|
|
civil plans required, provide vtr for west basement drainage, interceptor required for parking lot drainage with connection to sanitary sewer, provide design for garage drainage plans unclear, are the 2 8" -W- lines on p110 misidentified.
|
Routing - PUBLIC WORKS | 11/16/1999 | 11/16/1999 | 11/18/1999 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY AND REQUIRES STREET LIGHT PLAN PER BILL COLSON.. 11/18/99 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 11/16/1999 | | |
|
|
|
|
Application received | | | 11/12/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/12/1999 | | DONE |
|
|
|
no plan check fees due per Jeff Jones.
|