Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-03392
StatusFinaled
Name FOUR SEASONS TRAVEL
Site Address 1742 W STATE ST
Project NameALBERTSONS MARKETPLC
Customer Number 
ePlanReviewNo
Description
New tenant in a 1,609 sq.ft. space for use as office per approved plans on file. Previous "Vanilla Finish" permit done under BLD99-02961. Work to include interior walls with doors and windows, interior finish, some suspended ceiling adjustments, two new exterior doors out of existing restrooms, one new large exterior landing, possible fire sprinkler adjustments, some plumbing work, and some electrical work. Restrooms are existing and were approved under previous Boise City Policy letter (6/25/96) for an accessible single occupant use restroom. NOTE: This building is fully fire sprinklered for area increase. (P.C.#900-99) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes11/12/199911/12/19997/24/2000 DONE
Permanent occupancy UNPAID FEE  1/25/2000 DONE
Perm. Occ. Cert. #8106 issued 1-25-00 to Four Seasons Travel in the Albertson's Marketplace.
Permanent Occupancy 1/20/20001/20/2000 DONE
Details
BLD-Final1/19/20001/20/20001/20/2000APASS
Details
###-#### Richard c/n removed ok for perm signoff of the permit 1/20/00 11:48:27 AM
FIRE-Final Inspection12/14/199912/15/199912/15/1999APASS
DetailsRick Jackson
richard ###-#### Occupancy approved.
BLD-Final12/15/199912/15/199912/15/1999PPART
Details
don ###-#### fn occ Ok for temp. occ.
FIRE-Final Inspection12/14/199912/14/199912/14/1999PCANC
DetailsRick Jackson
don --###-#### fire fn Reschedule.
BLD-Framing/Rough-in12/13/199912/13/199912/13/1999PPASS
Details
Scheduled by a contractor via Hello! on 12/13/1999 at 10:54:51. Contact: ###-####.
Routing - PLAN CHECK12/7/199912/7/199912/13/1999 PASS
Plans approved and taken to front desk.
Plan assigned to (JCB)11/19/1999 12/13/1999 PASS
DetailsJason Blais
PLANS/APPL TAKEN TO FRONT DESK  12/13/1999  
Inspection Record Card- Bld  12/13/1999 DONE
Print Occupancy Form  12/13/1999 DONE
Telephone call  12/13/1999 DONE
###-#### left message Scott
Issue PAID IN FULL permit  12/13/1999 DONE
Plan resubmittals received  12/10/1999 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A1.0. ROUTED TO JASON B. KMM
Routing - FIRE12/6/199912/7/199912/7/1999 PASS
Plan Review Completed(1st rev)  12/7/1999 PEND
Plan resubmittals received  12/7/1999 DONE
PLAN RESUBMITTALS RECEIVED FROM PATRICK McKEEGAN ARCHITECT, SHEET A1.0 PLUS WRITTEN COMMENTS RECEIVED AND FORWARDED TO JASON BLAIS. 12/7/99 DAR
Plan resubmittals requested  12/6/1999 PEND
Resubmittal drawings required for further review.
Routing - PLAN CHECK11/22/1999 12/6/1999 FAIL
Plan review report sent and faxed to architect. Resubmittals and response required for further review. Plans routed to fire dept.
Routing - PUBLIC WORKS11/22/1999 11/22/1999 PASS
Pending Assignment by MYS11/19/1999 11/19/1999 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  11/19/1999 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  11/16/1999 PEND
Application received  11/12/1999  
Recd Pcfee & Taken To Pln CK  11/12/1999 DONE