BLD-Final | 10/27/2000 | 10/27/2000 | 10/27/2000 | | PASS |
|
|
|
L/C #19975
|
BLD-Grading Inspection | 10/27/2000 | 10/27/2000 | 10/27/2000 | | BOND |
Rita DeYoung
|
|
|
Grading completed according to plan. Compaction test results for fill beneath garage floor and driveway must still be submitted. Contractor provided estimate of $4000.00 for replacement of driveway.
|
BLD-Final | 10/25/2000 | 10/26/2000 | 10/26/2000 | A | FAIL |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 10/25/2000 by 9 am,mike ###-####
still need T. Records sign off 10/26/2000 12:42:42 PM
|
BLD-Final | 10/25/2000 | 10/25/2000 | 10/25/2000 | P | FAIL |
Tony Young
|
|
|
FN OCC-- MIKE ###-#### -CALL 1ST BEFORE INSP
need T.R signoff 10/25/2000 4:50:00 PM
|
BLD-Final | 10/24/2000 | 10/24/2000 | 10/24/2000 | P | FAIL |
Tony Young
|
|
|
MIKE- ###-#### FN OCC--
need plumbing, handrails x2, firewall, and T.Records sign off. 10/24/2000 3:46:48 PM
|
BLD-Framing/Rough-in | 7/20/2000 | 7/20/2000 | 7/20/2000 | P | PASS |
Tony Young
|
|
|
call 1st before insp mike-- ###-#### re-insp fr Ok to cover- shear ok- energy code ok 7/21/00 9:11:45 AM
|
BLD-Energy code compliance | 7/20/2000 | 7/20/2000 | 7/20/2000 | P | PASS |
Tony Young
|
|
|
Pass
|
BLD-Framing/Rough-in | 7/18/2000 | 7/19/2000 | 7/19/2000 | A | FAIL |
Tony Young
|
|
|
call 25 min. prior ###-#### to meet there Need mec. check- & finish shear nailing- waiting for letter from engineer. 7/19/00 3:27:12 PM
|
BLD-Framing/Rough-in | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | FAIL |
Tony Young
|
|
|
MIKE ###-#### FR-CALL 1/2 HR BEFORE INSP PLEASE C/N left need to finish 1st C/N- need eng. on shear wall to plans. (eng. brace panels). 7/14/00 8:58:46 AM
|
BLD-Framing/Rough-in | 7/12/2000 | 7/12/2000 | 7/12/2000 | P | FAIL |
Tony Young
|
|
|
###-#### C/N previous not done. 7/13/00 11:29:36 AM
|
BLD-Energy code compliance | 7/11/2000 | 7/11/2000 | 7/11/2000 | A | FAIL |
|
|
|
Scheduled by Inspector: 338 On 7/11/00 to meet with 415 and Mike..###-#### combustables in concealedspaces; stair bottom tread heght to be confirmed; seal floor to wall at the attic truss floor to the attic wall; remove vapor barrier from behind the green board on ext walls 7/11/00 11:15:43 AM
|
BLD-Framing/Rough-in | 7/10/2000 | 7/10/2000 | 7/10/2000 | P | FAIL |
|
|
|
Mike ###-#### need to meet 415 on site 7/10/00 5:56:11 PM
|
BLD-Framing/Rough-in | 7/6/2000 | 7/7/2000 | 7/7/2000 | A | NR |
Russ Owen
|
|
|
###-####
|
BLD-Framing/Rough-in | 7/3/2000 | 7/3/2000 | 7/3/2000 | P | FAIL |
Tony Young
|
|
|
###-#### plans in truss engineering by fireplace c/n left 9 items 7/5/00 8:38:16 AM
|
BLD-Foundation | 5/9/2000 | 5/9/2000 | 5/9/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/09/2000 at 08:37:15. Contact: ###-####. rear portion of te 5/9/00 7:55:41 PM Scheduled by a contractor via Hello! on 05/09/2000 at 08:37:15. Contact: ###-####. rear portion of the foundation and infill footings ok to pour 5/9/00 7:55:41 PM 5/9/00 7:56:26 PM
|
BLD-Footing | 5/4/2000 | 5/4/2000 | 5/4/2000 | P | PASS |
Russ Owen
|
|
|
mike --###-#### ft---re-insp
|
BLD-Footing | 5/2/2000 | 5/3/2000 | 5/3/2000 | A | FAIL |
Russ Owen
|
|
|
###-#### C/N posted 5/4/00 11:31:11 AM
|
Issue PAID IN FULL permit | | | 4/28/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/24/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/28/2000 | | DONE |
|
|
|
called talked to jim faxed over copy of permit fees - also told them if they are needing to void plans that there will be a plan check fee of over 400.00-mps he will call me on monday
|
Plan assigned to (DJO) | 12/3/1999 | 12/3/1999 | 1/10/2000 | | PASS |
Dan Overy
|
|
|
1/10/2000 14:09:20 SAM - activity updated through activity BLDA022 from case BLD99-03405.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/10/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/10/2000 | | DONE |
|
|
|
called gave dollar amount told them they need another site plan. will bring in when they pick up permit.mps
|
Routing - PLANNING | 12/23/1999 | 12/23/1999 | 12/27/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 11/15/1999 | 11/15/1999 | 12/23/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/3/1999 | 12/3/1999 | 12/23/1999 | | DONE |
|
|
|
sent back to terry records 12/03/99
|
Routing - PUBLIC WORKS GRADING | 11/15/1999 | 11/15/1999 | 12/23/1999 | | PASS |
Rita DeYoung
|
|
|
took to terry records
Soils report did not include tests on the expansiveness of the clay soils that were indicated onsite. Talked to David Cram at MTI and requested additional information on the clay and opinions on the affect it may have on the foundation
of the house. Took the house plans to Dan Overy on 11/23/99.
Soils report was modified and approved. It indicated a layer of expansive clay and recommended that the footings be placed beneath this layer
|
Application received | | | 11/15/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 12/27/1999 | 12/27/1999 | | | PEND |
|
|
|
|
Print permit w/o conditions | | | | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Pending Assignment by DJO | 11/15/1999 | | | | PEND |
Dan Overy
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | | | |
|
|
|
plans have not been approved by public works or zoning. were routed for initial structural plan review. additional information will be required when officially routed to this department.
|
Plan Reviewer's activity | | | | | |
|
|
|
roof framing package to be provided from truss manufacturer. information needed to comply with natural light req.
|