Fee Review-notes | 11/22/1999 | 11/22/1999 | 7/24/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 6/19/2000 | 6/19/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 6/19/2000 | | DONE |
|
|
|
owing $33.00 for sprinkler only - occ. #8264
|
BLD-Final | 6/15/2000 | 6/15/2000 | 6/15/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/15/2000 at 08:44:08. Contact: ###-####. Ok for perm 6/16/00 2:09:12 PM
|
BLD-Final | 6/14/2000 | 6/14/2000 | 6/14/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 07:44:30. Contact: ###-####. Not ready 6/16/00 8:51:05 AM
|
FIRE-Final Inspection | 6/12/2000 | 6/13/2000 | 6/13/2000 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/12/2000 at 15:44:50. Contact: ###-####. Reinsp. ok for perm. occ. 6/13/00 2:43:35 PM
|
Code Occupancy Approval | | | 6/6/2000 | | PASS |
|
|
|
Meets compliance with DRH99-00231. Pass
|
FIRE-Final Inspection | 6/5/2000 | 6/5/2000 | 6/5/2000 | P | FAIL |
Joe Tawney
|
|
|
Matt ###-#### Final fail C/N issued. 6/6/00 11:28:13 AM
|
BLD-Other | 5/24/2000 | 5/24/2000 | 5/24/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/24/2000 at 09:18:15. Contact: ###-####. Conf. on guard rail 5/25/00 9:01:04 AM
|
BLD-Other | 5/23/2000 | 5/23/2000 | 5/23/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/23/2000 at 09:58:32. Contact: ###-####. Grid ok and conf. 5/24/00 11:13:28 AM
|
BLD-Conference | 4/18/2000 | 4/18/2000 | 4/18/2000 | A | PASS |
Tom Arcoraci
|
|
|
Counter height in lounge/lab changed from 34 to 36 inches per architects letter.
|
BLD-Conference | 4/11/2000 | 4/12/2000 | 4/12/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/11/2000 at 14:05:44. Contact: ###-####. Conf. on computers 4/12/00 2:34:43 PM
|
BLD-Framing/Rough-in | 3/23/2000 | 3/24/2000 | 3/24/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/23/2000 at 14:09:50. Contact: ###-####. 1hr. "gas" room ok 3/24/00 2:03:30 PM
|
BLD-Framing/Rough-in | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | FAIL |
Tom Arcoraci
|
|
|
matt ###-#### fr Need HVAC R/I and finish 1st C/N 3/14/00 2:01:28 PM
|
BLD-Framing/Rough-in | 3/10/2000 | 3/13/2000 | 3/13/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/10/2000 at 15:30:37. Contact: ###-####. N/R; recall. 3/14/00 1:29:49 PM
|
BLD-Framing/Rough-in | 3/13/2000 | 3/13/2000 | 3/13/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### Work not complete per contractor; recall. 3/14/00 1:47:14 PM
|
BLD-Framing/Rough-in | 3/7/2000 | 3/8/2000 | 3/8/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/07/2000 at 16:54:35. Contact: ###-####. See C/N. 3/9/00 11:38:06 AM
|
BLD-Framing/Rough-in | 2/24/2000 | 2/25/2000 | 2/25/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### would like to have this before 3:00 if at all possible. C/N need eng's ok for deletion of connection @ "struct. fascia" WIP 408's area 2/28/00 2:46:56 PM
|
BLD-Foundation | 2/2/2000 | 2/2/2000 | 2/2/2000 | P | PART |
Tom Arcoraci
|
|
|
###-#### ok pending spec inspec report 2/3/00 9:21:12 AM
|
BLD-Footing | 1/31/2000 | 2/1/2000 | 2/1/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### spec insp on site 2/1/00 2:11:34 PM
|
BLD-Foundation | 2/1/2000 | 2/1/2000 | 2/1/2000 | P | PART |
Tom Arcoraci
|
|
|
Matt; ###-####. pending spec insp report 2/3/00 7:34:50 AM
|
(F) Reprint permit | | | 1/24/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/21/2000 | | DONE |
|
|
|
|
Routing - FIRE | 12/7/1999 | 12/9/1999 | 12/9/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/9/1999 | 12/9/1999 | 12/9/1999 | | |
|
|
|
|
Plan assigned to (M_P) | 11/24/1999 | 11/24/1999 | 12/9/1999 | | PASS |
Mike Phillips
|
|
|
12/9/1999 11:07:41 M_P - activity updated through activity BLDA022 from case BLD99-03469.
|
Routing - PLAN CHECK | 12/2/1999 | | 12/9/1999 | | PEND |
|
|
|
|
Plan assigned to (M_P) | 11/23/1999 | | 12/9/1999 | | PASS |
Mike Phillips
|
|
|
12/9/1999 11:07:41 M_P - activity updated through activity BLDA022 from case BLD99-03469.
|
Plan Reviewer's activity | | | 12/9/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/1999 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/9/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/9/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/9/1999 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/9/1999 | | DONE |
|
|
|
|
Telephone call | | | 12/9/1999 | | DONE |
|
|
|
called Wright Brothers Brandon Fonnesbeck left voice mail permit ready and fees due.
|
Plan Review Completed(1st rev) | | | 12/9/1999 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 12/7/1999 | | PEND |
|
|
|
pENDING APPROVAL OF FIRE DEPARTMENT.
|
Print Pending Permit.LaserJet4 | | | 12/7/1999 | | PEND |
|
|
|
ROUTING TO FIRE DEPERTMENT FOR APPROVAL PRIOR TO ISSUING PERMIT.
|
Routing - PLUMBING | 11/29/1999 | | 12/2/1999 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 11/24/1999 | 11/24/1999 | 11/29/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 11/29/1999 | | 11/29/1999 | | PASS |
|
|
|
approved per DRH99-00231.
|
Received Certificate of Value | | | 11/24/1999 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 11/24/1999 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/24/1999 | | DONE |
|
|
|
|
Application received | | | 11/22/1999 | | |
|
|
|
|
Pending Assignment by MYS | 11/22/1999 | | | | |
Marlene Southard
|
|
|
|