Letter of compliance | | | 1/17/2002 | | DONE |
|
|
|
Letter of Compliance #22134 issued 1-17-02.
|
(F) Reprint permit | | | 1/16/2002 | | DONE |
|
|
|
|
BLD-Final | 1/15/2002 | 1/15/2002 | 1/15/2002 | | PASS |
Jim Storey
|
|
|
final ok
|
FIRE-Final Inspection | 7/31/2001 | 7/31/2001 | 7/31/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 7/31/2001 9:57:58 AM
|
BLD-Framing/Rough-in | 9/21/2000 | 9/22/2000 | 9/22/2000 | A | PASS |
Jim Storey
|
|
|
Bob Cafferty, ###-####
|
FIRE-Sprinkler Rough-in | 9/21/2000 | 9/22/2000 | 9/22/2000 | A | PART |
Rick Jackson
|
|
|
Bill Cafferty, ###-####
|
BLD-Framing/Rough-in | 9/18/2000 | 9/19/2000 | 9/19/2000 | A | PASS |
Jim Storey
|
|
|
###-####
|
Inspection Record Card- Bld | | | 9/14/2000 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 5/18/2000 | 5/18/2000 | 5/18/2000 | P | PART |
|
|
|
bob ###-#### fr with bob &co walked the restrooms etc. common sence seems appropriate bob now has copies of dimensions from the 1992 cabo ansi . will b in touch with 301 5/18/00 3:53:30 PM
|
FIRE-Sprinkler Rough-in | 5/18/2000 | 5/18/2000 | 5/18/2000 | P | PASS |
Rick Jackson
|
|
|
bob ###-#### fire r/i Okay to cover. 5/22/00 9:01:18 AM
|
Fee Review-notes | 12/3/1999 | 12/3/1999 | 3/15/2000 | | DONE |
|
|
|
|
FIRE-Sprinkler Rough-in | 2/16/2000 | 2/17/2000 | 2/18/2000 | A | PART |
Rick Jackson
|
|
|
Bob Cafferty, ###-#### Ok on spklr. r/I. 2/18/00 3:26:42 PM
|
BLD-Framing/Rough-in | 2/2/2000 | 2/3/2000 | 2/3/2000 | A | PART |
Jim Storey
|
|
|
###-#### Ok pend. Ele. 2/4/00 11:52:41 AM
|
BLD-Framing/Rough-in | 1/24/2000 | 1/25/2000 | 1/25/2000 | A | PART |
|
|
|
Bob Cafferty, ###-#### made ok to cover interior walls with the elec insp blessing 1/26/00 8:05:13 AM
|
Issue PAID IN FULL permit | | | 1/20/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 12/8/1999 | | 1/11/2000 | | PASS |
Jason Blais
|
|
|
|
Routing - PLAN CHECK | 1/7/2000 | | 1/11/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2000 | | |
|
|
|
|
Print Occupancy Form | | | 1/11/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2000 | | DONE |
|
|
|
TALKED TO JENIFER GAVE DOLLAR AMOUNT
|
Routing - FIRE | 12/29/1999 | 1/7/2000 | 1/7/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/7/2000 | | |
|
|
|
|
Plan resubmittals received | | | 1/4/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HOSFORD, LARSON, RUDEEN FORDWARDED SAME TO JASON BLAIS, ARCHITECTURAL SHEETS AND A ARCHITECT OF RECORD FORM. 1/4/99 DAR
|
Plan resubmittals requested | | | 12/29/1999 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 12/8/1999 | | 12/29/1999 | | FAIL |
|
|
|
Plan review report given to architect. Resubmittal drawings and response required for further review. Architect of Record form still needed. Plans routed to fire dept. for review.
|
Routing - PUBLIC WORKS | 12/8/1999 | | 12/8/1999 | | DONE |
|
|
|
|
Pending Assignment by MYS | 12/3/1999 | | 12/8/1999 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 12/8/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 12/6/1999 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/3/1999 | | DONE |
|
|
|
|
Application received | | | 12/3/1999 | | |
|
|
|
|