Case Summary (BLD) | | | 3/9/2001 | | DONE |
|
|
|
|
Fee Review-notes | 12/8/1999 | 12/8/1999 | 11/27/2000 | | DONE |
|
|
|
additional values from the subs...
|
Letter of compliance | | | 10/25/2000 | | DONE |
|
|
|
Letter of Compliance #19969 issued 10-25-00.
|
BLD-Final | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PASS |
Jim Storey
|
|
|
###-####
|
Print Occupancy Form | | | 9/29/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/26/2000 | 9/27/2000 | 9/27/2000 | A | NR |
Rick Jackson
|
|
|
Israel ###-#### not a final inspection - sprinkler r/i okay to cover 9/27/2000 9:59:02 AM
|
FIRE-Sprinkler Rough-in | 9/27/2000 | 9/27/2000 | 9/27/2000 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 9/27/2000 okay to cover
|
BLD-Framing/Rough-in | 9/26/2000 | 9/26/2000 | 9/26/2000 | P | PASS |
Jim Storey
|
|
|
ceiling Shawn ###-####
|
BLD-Framing/Rough-in | 9/22/2000 | 9/22/2000 | 9/22/2000 | P | FAIL |
Jim Storey
|
|
|
ceiling shawn ###-#### c/n lights supports/ gyp protection type 3 1hr. 9/25/2000 10:17:15 AM
|
BLD-Framing/Rough-in | 9/22/2000 | 9/22/2000 | 9/22/2000 | P | FAIL |
Jim Storey
|
|
|
ceiling shawn ###-#### c/n lights supports/ gyp protection type 3 1hr. 9/25/2000 10:17:15 AM
|
BLD-Framing/Rough-in | 9/5/2000 | 9/6/2000 | 9/6/2000 | A | PASS |
|
|
|
###-#### ok to cover header not needed 9/7/2000 3:11:47 PM
|
BLD-Framing/Rough-in | 9/1/2000 | 9/5/2000 | 9/5/2000 | A | PART |
|
|
|
shawn ###-#### need header over entry to restrooms 9/6/2000 9:36:49 AM
|
BLD-Framing/Rough-in | 8/31/2000 | 9/1/2000 | 9/1/2000 | A | PART |
|
|
|
###-#### ok to cover pending review by inspector of the approved plans while on the jobsite 9/1/2000 4:08:36 PM
|
Routing Off Site - A.C.H.D | 8/4/2000 | 8/4/2000 | 8/4/2000 | | DONE |
|
|
|
No achd needed for this project>mps8/4/00
|
Telephone call | | | 8/4/2000 | | DONE |
|
|
|
called left message gave dollar amount
|
Issue PAID IN FULL permit | | | 8/4/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/4/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/3/2000 | | PASS |
|
|
|
Resubmitted drawings approved, with conditions and "red lines", after review.
|
CHANGE STATUS TO (PND) | | | 8/3/2000 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2000 | | PASS |
|
|
|
|
Telephone call | | | 8/3/2000 | | DONE |
|
|
|
Carl Westfall pulled plans from drawer 8/3/00
|
Plan resubmittals received | | | 7/28/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED M-1 SHEET AND ONE COPY OF REVISED CERT. OF VALUE. ROUTED TO CARL W. KMM
|
Plan resubmittals received | | | 7/27/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS 0.1, 0 4, 20.0, 20.1, M-1 ROUTED TO CARL W. KMM
|
Plan resubmittals received | | | 7/27/2000 | | PASS |
|
|
|
Resubmittals received. Restrooms redesigned. Mechanical work expanded to included making outside air available to all floors.
|
Telephone call | | | 3/27/2000 | | DONE |
|
|
|
tried to call no answer or answering machine-mps3/27/00
|
Routing - PLAN CHECK | 1/5/2000 | | 1/7/2000 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/7/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/7/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/7/2000 | | DONE |
|
|
|
TALKED TO JOHN MAHONEY-TO VERIFY PLANS ARE READY
|
Plan assigned to (CJW) | 12/9/1999 | | 1/7/2000 | | PASS |
Carl Westfall
|
|
|
1/7/00 12:40:53 CJW - activity updated through activity BLDA022 from case BLD99-03588.
|
Routing - FIRE | 12/28/1999 | 1/5/2000 | 1/5/2000 | | PASS |
Sam Rogers
|
|
|
|
Plan Review Completed(1st rev) | | | 1/5/2000 | | PASS |
Sam Rogers
|
|
|
|
Routing - PLUMBING | 12/22/1999 | | 12/28/1999 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/14/1999 | | 12/22/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/21/1999 | | PASS |
|
|
|
UBC plan review started December 21, 1999 and finished December 22, 1999. The drawings were approved with conditions. See the conditions list.
|
Routing - PUBLIC WORKS | 12/9/1999 | | 12/14/1999 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 12/9/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 12/9/1999 | | DONE |
|
|
|
CERTIFICATE OF VALUE NOT COMPLETELY FILLED IN, CONTACTED JOHN MAHONEY AND HE WILL TAKE CARE OF THE PROBLEM. 12/9/99 DAR
|
Pending Assignment by MYS | 12/9/1999 | | 12/9/1999 | | DONE |
Marlene Southard
|
|
|
|
Application received | | | 12/8/1999 | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|