Case Summary (BLD) | | | 7/11/2011 | | |
|
|
|
|
Fee Review-notes | 12/10/1999 | 12/10/1999 | 5/5/2000 | | DONE |
|
|
|
|
Letter of compliance | | | 3/24/2000 | | DONE |
|
|
|
Letter of Compliance #18389 issued 3-24-00.
|
BLD-Final | 3/22/2000 | 3/23/2000 | 3/23/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/22/2000 at 10:42:49. Contact: . OK for perm. 3/24/00 9:32:38 AM
|
BLD-Final | 3/21/2000 | 3/21/2000 | 3/21/2000 | P | PASS |
Joe Tawney
|
|
|
Final ok for certificate of completion.
|
FIRE-Alarm Testing | 3/8/2000 | 3/14/2000 | 3/14/2000 | P | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/08/2000 at 11:50:17. Contact: ###-####. Inspection cancelled submittals not approval. 3/16/00 11:19:51 AM
|
Receive PAYMENT IN FULL | | | 2/15/2000 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 12/23/1999 | 12/29/1999 | 12/29/1999 | P | PART |
Tom Arcoraci
|
|
|
dan ###-#### r/i. Ok to cover lower level.
|
FIRE-Final Inspection | 12/29/1999 | 12/29/1999 | 12/29/1999 | P | PASS |
Joe Tawney
|
|
|
Final alarm system upgrade pass.
|
Inspection Record Card- Bld | | | 12/21/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/21/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/21/1999 | | DONE |
|
|
|
|
Telephone call | | | 12/21/1999 | | DONE |
|
|
|
talked to debbie to verify plans are ready
|
Issue & PRINT FEE-DUE permit | | | 12/21/1999 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/1999 | | PASS |
|
|
|
Processing for issuance of permit based on plan review comments & cover letter.
|
Plan assigned to (DRS) | 12/15/1999 | | 12/20/1999 | | PASS |
Dan Stuart
|
|
|
12/20/1999 14:33:26 DRS - activity updated through activity BLDA022 from case BLD99-03607.
|
Routing - PLAN CHECK | 12/15/1999 | | 12/20/1999 | | PASS |
|
|
|
APPROVED AS NOTED AND PER ATTACHED PLAN REVIEW COMMENTS & COVER LETTER. REVIEWED SCOPE WITH BILL ALEXANDER TO SEE IF HE NEEDED TO REVIEW PLANS. NOT REQUIRED.
|
Routing - FIRE | 12/20/1999 | | 12/20/1999 | | |
|
|
|
HAD BILL ALEXANDER COME TO MY CUBICLE TO REVIEW SCOPE OF WORK. DOES NOT INVOLVE ANY NEW WALLS BELOW CEILING SO THE EXISTING SPRINKLER SYSTEM PLACEMENT SHOULD STILL PROVIDE REQUIRED COVERAGE. HOWEVER I HAVE NOTED AS A CONDITION OF FINAL APPROVAL THAT THE FIRE INSPECTOR REVIEW THE EXISTING SITUATION FOR ANY REQUIRED UPGRADES OF SPRINKLER OR ALARM SYSTEM THAT HAVE BEEN AFFECTED BY THIS PROJECT SCOPE. drs
|
Plan routing begun/TENANTS | | | 12/15/1999 | | DONE |
|
|
|
Route to PLAN CHECK and FIRE.
|
Pending Assignment by MYS | 12/15/1999 | | 12/15/1999 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/13/1999 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/13/1999 | | DONE |
|
|
|
|
Application received | | | 12/10/1999 | | |
|
|
|
|
Meeting | | | 12/6/1999 | | |
|
|
|
Met with John Maulin & associate to review the scope of the 1-hour occupancy separation /corridor upgrade to improve compliance with original requirements for separation & construction for an "A2.1 & "B" occupancy in HP#3. We have been working on getting approval from HP to work on this construction upgrade since mid 1996 when it was discovered that the original code review requirements had not been completed. Additional work is needed in other parts of the "A2.1", "A3" & "B", 1-story portion, that are being reviewed and we will continue to make progressive steps until completed.
|