Letter of compliance | | | 12/1/2000 | | DONE |
|
|
|
Letter of Compliance #20035 issued 12-1-00.
|
BLD-Final | 11/29/2000 | 11/30/2000 | 11/30/2000 | A | PASS |
Russ Owen
|
|
|
Jerry ###-####
|
Fee Review-notes | 12/15/1999 | 12/15/1999 | 11/27/2000 | | DONE |
|
|
|
|
BLD-Conference | 11/24/2000 | 11/24/2000 | 11/24/2000 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/24/2000 9:42:56 AM w/ Ben Hill SCP arch...ER-HDR won't stamp letters...consult w/ 305???
|
Temporary occupancy | | | 11/17/2000 | | PART |
|
|
|
Temp. Occ. Cert. #4082 issued 11-17-00 to SCP Global Technologies.
|
FIRE-Final Inspection | 11/14/2000 | 11/16/2000 | 11/16/2000 | A | CANC |
Joe Tawney
|
|
|
JERRY ###-#### FIRE FN Cancel To be resched to 11/16/00 11/15/2000 12:18:07 PM
|
BLD-Final | 11/14/2000 | 11/16/2000 | 11/16/2000 | P | CANC |
Steven Webb
|
|
|
JERRY ###-#### FN: Transfer to Carl 11/16/2000 1:40:41 PM
|
FIRE-Final Inspection | 11/15/2000 | 11/16/2000 | 11/16/2000 | A | PASS |
Joe Tawney
|
|
|
###-#### Final OK for certificate of completion 11/16/2000 12:55:28 PM
|
BLD-Final | 11/15/2000 | 11/16/2000 | 11/16/2000 | P | CANC |
Steven Webb
|
|
|
###-####: To Carl 11/16/2000 1:41:43 PM
|
BLD-Final | 11/16/2000 | 11/16/2000 | 11/16/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/16/2000 5:46:53 PM need stamped eng's letter, review discrepancies. ok for t/o
|
Plan resubmittals received | | | 11/7/2000 | | DONE |
|
|
|
Received one copy of testing and inspection reports. routed to Dan Stuart. KMM
|
BLD-Framing/Rough-in | 10/25/2000 | 10/26/2000 | 10/26/2000 | A | FAIL |
Carl Dependahl
|
|
|
FR JERRY ###-#### c/n, stairs,, dampe 10/26/2000 6:05:43 PM s, etc 10/26/2000 6:05:57 PM
|
BLD-Footing | 4/18/2000 | 4/18/2000 | 4/18/2000 | P | PART |
Carl Dependahl
|
|
|
###-#### "Pad & ftg's". 4/19/00 9:18:30 AM
|
BLD-Footing | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-####-jerry ft
|
BLD-Footing | 4/12/2000 | 4/13/2000 | 4/13/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### Spec. insp. 4/13/00 1:04:32 PM
|
BLD-Conference | 2/14/2000 | 2/14/2000 | 2/14/2000 | P | PASS |
Carl Dependahl
|
|
|
REVIIEWED SPEC INSP AGREEMENT & REPORTS; PARTIAL PERMIT ONLY FOR PROJECT AT THIS TIME
|
BLD-Other | 2/3/2000 | 2/4/2000 | 2/4/2000 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 09:20:49. Contact: ###-####. Met w/ eng'r & spec insp onsite (MTI) Agreement letter forthcoming. WIP ok
|
BLD-Footing | 1/24/2000 | 1/25/2000 | 1/25/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/24/2000 at 11:37:38. Contact: ###-####. per 340 made ok to pour pending sp insp documents 1/26/00 8:06:31 AM
|
BLD-Footing | 1/20/2000 | 1/24/2000 | 1/24/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/20/2000 at 16:43:22. Contact: ###-####. c\n seal corrodor walls ok to infill need lites wired and grid 1/31/00 8:59:46 AM
|
Print Occupancy Form | | | 1/20/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/20/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/20/2000 | | DONE |
|
|
|
called left message on machine gave dollar amount###-####
|
Issue PAID IN FULL permit | | | 1/20/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/11/2000 | 1/11/2000 | 1/19/2000 | | PASS |
|
|
|
Response from architect to structural plan review clarifications & corrections received 1/10/2000. Inserted copies into original plan submittals & routed copies to outside engineering for re-review.
1/11/00 - Copy of plan review comments faxed & mailed to architect. Need the special inspection forms completed by having special inspection agency assigned and forms signed & dated - copies to go to structural inspector, Carl Dependahl.
1/19/00 - Received written approval from Howie Hennrikson, CH2M HILL, that structural review was approved based on resubmittals received. Processing for issuance of structural permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2000 | | PASS |
|
|
|
Processing for issuance of permit.
|
Plan assigned to (DRS) | 12/15/1999 | | 1/19/2000 | | PASS |
Dan Stuart
|
|
|
1/19/2000 16:54:20 DRS - activity updated through activity BLDA022 from case BLD99-03639.
|
Routing Off Site - STRUCTURAL | 12/15/1999 | | 1/18/2000 | | PASS |
|
|
|
SENT PLANS TO CONSULTING STRUCTURAL ENGINEER VIA PDQ. (DAR)
1/18/00 - Received written notification from Howie Hennrikson, CH2MHILL, performing 3rd party structural review of SCP Substructure plans, that the resubmittals resolved previous concerns and that the structural data submitted and reviewed has been approved. drs
|
Plan resubmittals received | | | 1/10/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ER + HDRDRAWINGS A3.3, S2.1.3. AND S5.2.2.3, FORWARDED SAME TO DAN STUART. 1/10/00 DAR
|
Plan Reviewer's activity | | | 1/3/2000 | | |
|
|
|
Received report from outside structural engineering firm concerning plan review of sub-structure for SCP Global Tech. Resubmittals required from engineering & architectural detail for existing column penetrations of new interior subroof decking for review of deflection allowance. Re- Review by outside engineering required when new submittals received. Faxed copy of report to Tony Ray, ER+HDR, & Riley at Atwood-Hinzman-Jones, Structural Design Engineers for response.
|
Plan resubmittals requested | | | 1/3/2000 | | |
|
|
|
Report from outside engineering review of substructure for SCP Global Technologies received. Resubmittal response required concerning structural design analysis from outside third party engineering firm. Copy of report faxed and mailed to Tony Ray, ER+HDR Architects, & Riley, AHJ Design Engineers for response. Required to be submitted to outside engineering firm contracted with Boise City for additional review when response received.
|
Routing - PLAN CHECK | 12/15/1999 | 12/15/1999 | 12/15/1999 | | PEND |
|
|
|
Plans routed to contracted third party outside engineering firm for review of structural design.
|
Recd Pcfee & Taken To Pln CK | | | 12/15/1999 | | DONE |
|
|
|
|
Application received | | | 12/15/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/1999 | | PEND |
|
|
|
|
Pending Assignment by MYS | 12/15/1999 | | 12/15/1999 | | DONE |
Marlene Southard
|
|
|
|
Routing Off Site - STRUCTURAL | 1/11/2000 | | | | PEND |
|
|
|
SENT RESUBMITTALS TO CONSULTING STRUCTURAL ENGINEER VIA PDQ. 1/11/00 DAR
|