Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-03680
StatusFinaled
Name COLUMBIA VILLAGE LDS CHURCH
Site Address 3800 E GRAND FOREST DR
Project Name 
Customer Number 
ePlanReviewNo
Description
COLUMBIA VILLAGE * GRADING PERMIT * TO GRUB, CLEAN, EXCAVATE, GRADE IMPORT AND COMPACT SITE EARTH MATERIALS IN PREPARATION FOR THE FUTURE CONSTRUCTION OF THE COLUMBIA VILLAGE LDS CHURCH. TO INSTALL CURB, GUTTER AND PAVING IN ACCORDANCE WITH THE GRADING AND DRAINAGE PLANS APPROVED BY THE PUBLIC WORKS DEPARTMENT. RELATED SITE UTILITIES ARE INCLUDED IN THIS PERMIT.NO CONSTRUCTION IS ALLOWED UNDER THIS PERMIT. CUP 99-00005, PC#986-99 NO PLANS ISSUED WITH THIS PERMIT. PLANS WILL BE ISSUED WITH THE FULL BUILDING PERMIT (BLD99-03673) DAR
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/20/20018/20/20018/20/2001 PASS
DetailsSteven Webb
project completed 8/20/2001 9:34:54 AM
DOC - Permit Finaled8/20/20018/20/20018/20/2001APASS
DetailsSteven Webb
Finaled by inspector at 8/20/2001 9:34:57 AM
Issue PAID IN FULL permit  8/17/2001 DONE
Telephone call  6/28/2001 DONE
called bill left message for him to call me.6/28/01-10:00 bill called me told him that he needs to come in and pick up grading permit. he will call the contractor and get back with me today.
PubWorks Occupancy Approval  3/30/2001 DONE
Drainage project complete 03/30/01. R.Cummings
BLD-Footing8/21/20008/22/20008/22/2000ACANC
DetailsRuss Owen
this permit is for grading and has not ever been issued...thought I would let you know because there are fees due. Please call me if you have any other questions. Thanks Linda ,I do not inspect grading. 8/22/2000 1:32:09 PM
(F) Reprint permit  8/21/2000 DONE
Inspection Record Card- Bld  7/5/2000 DONE
Telephone call  7/5/2000 DONE
called Bill Waite at ###-#### permit ready for pick up
Routing - PLAN CHECK1/26/2000 7/5/2000 PASS
Routing - FIRE6/28/20006/28/20006/28/2000 PASS
DetailsBill Alexander
Provided (1) plan of revised utility lines (fire and Hydrant lines).
Telephone call  6/28/2000 DONE
Faxed copy of "DEMIED" review and a letter of requirement and history. Letter threatened a "Stop Work" order. Ronad Thurber called and walked a plan over for review and appears acceptable.
PLANS/APPL TAKEN TO FRONT DESK  6/28/2000  
Architect claimed they hadn't received copy of 6/28/00 approved review. Refaxed approved review to architect and approved plans taken to front desk for issuing GRADING permit. (Bldg permit was inadvertently issued while this grading permit was DENIED). SLR.
Routing - FIRE1/19/20001/20/20001/20/2000 FAIL
Sprinkler supply and hydrant on the same supply connection.
Telephone call  1/19/2000 FAIL
Called Ron Thurber and gave him the problem with the new submittal not meeting BCC code. Indicated he will get site engineer to give me a call.
Routing - FIRE1/6/20001/7/20001/7/2000 FAIL
FOR GRADING AND DRAINAGE PLAN CHECK ONLY. 1/6/00
Need new hydrant, water supply information for fire sprinkler design. and hydrant flow verification. Fire line, hydrant and water supply (fire sprinkler water supply data) to show on plans.
Plan Review Completed(1st rev)  1/7/2000 FAIL
Hydrant location exceed limits allowed by the UFC. Setback to great.
Routing - PLANNING1/4/2000 1/6/2000 PASS
Routing - PLUMBING12/28/1999 1/4/2000 PASS
Routing - PUBLIC WORKS12/21/1999 12/28/1999 DONE
Application received  12/21/1999  
Plans ACCEPTED BY PLAN TECH  12/21/1999