Letter of compliance | | | 5/31/2000 | | DONE |
|
|
|
Letter of Compliance #18495 issued 5-31-00.
|
Receive PAYMENT IN FULL | | | 5/30/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/22/2000 | 5/22/2000 | 5/22/2000 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 5/22/2000 | 5/22/2000 | 5/22/2000 | P | PASS |
Jim Storey
|
|
|
###-#### L/C ok for issue 5/23/00 2:32:28 PM
|
Print Occupancy Form | | | 5/9/2000 | | DONE |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 2/2/2000 | | DONE |
|
|
|
|
Routing - FIRE | 1/11/2000 | 1/24/2000 | 1/31/2000 | | PASS |
|
|
|
1/19/2000 FED EXED OFFICE COPY TO FLOYD V. PER BILL A. KMM
1/28/2000 RECEIVED OFFICE COPY BACK FROM FLOYD. FAXED RESPONSE COMMENTS TO ARCH. ROUTE PLANS TO BILL A. KMM
|
Plan assigned to (JCM) | 12/22/1999 | | 1/31/2000 | | PASS |
John Menard
|
|
|
1/31/2000 10:07:44 JCM - activity updated through activity BLDA022 from case BLD99-03696.
|
Routing - PLAN CHECK | 1/31/2000 | | 1/31/2000 | | PASS |
|
|
|
1/31/2000 ROUTED OFFICE COPY BACK TO JOHN M. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/31/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/31/2000 | | DONE |
|
|
|
|
Telephone call | | | 1/31/2000 | | DONE |
|
|
|
I e-mailed them to let them know that the permit is ready
|
Plan Review Completed(1st rev) | | | 1/24/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 1/10/2000 | | 1/11/2000 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 1/11/2000 | | PASS |
|
|
|
I e-mailed Terry Mattson at Micron to request additional information on the use of the building link between Buildings #2 and #5. The concern was whether the link was being used as a required exit from building #2. I received a telephone call from David White, project architect of record, addressing this concern. He indicated that Micron does not use any of their pedestrian links between buidings as a required means of egress.
|
Routing - FIRE | 1/3/2000 | 1/10/2000 | 1/10/2000 | | FAIL |
|
|
|
Need more information on exiting issues per John Menard's comments
|
Plan Review Completed(1st rev) | | | 1/10/2000 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 1/4/2000 | | DONE |
|
|
|
Received plan resubmittals from micron,page 1. 1/4/99 DAR
|
Routing - PLAN CHECK | 12/23/1999 | | 1/3/2000 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 1/3/2000 | | PEND |
|
|
|
E-MAILED TERRY MATTSON A COPY OF THE COVER LETTER AND COMMENT LIST REQUESTING REVISIONS.
|
Routing - PUBLIC WORKS | 12/22/1999 | | 12/23/1999 | | DONE |
|
|
|
|
Application received | | | 12/22/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/22/1999 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/22/1999 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 12/22/1999 | | |
|
|
|
|