Final | 11/10/2000 | 11/13/2000 | 11/13/2000 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/10/2000 at 16:32:55. Contact: ###-####. completed. 11/13/2000 11:35:33 AM
|
DOC - Permit Finaled | 11/13/2000 | 11/13/2000 | 11/13/2000 | A | PASS |
Marv Burrus
|
|
|
Added by Inspector: 403 On 11/13/2000
|
Final | 11/8/2000 | 11/9/2000 | 11/9/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/08/2000 at 09:12:39. Contact: ###-####. temporary occupancy only ; roof-top units, sign lighting, & strapping of flex-conduit @ counters not completed. 11/9/2000 11:46:28 AM
|
Electrical Rough-In | 10/25/2000 | 10/25/2000 | 10/25/2000 | P | PASS |
Marv Burrus
|
|
|
CEILING INSP -DICK ###-####. r/i. 10/25/2000 5:23:42 PM
|
Electrical Rough-In | 9/27/2000 | 9/27/2000 | 9/27/2000 | P | PASS |
Jim Schmer
|
|
|
###-####
|
Rough-In Permanent Service | 9/15/2000 | 9/15/2000 | 9/15/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/15/2000 at 07:04:45. Contact: ###-####. meter/main service gear. 9/16/2000 9:58:23 PM
|
Rough-In Permanent Service | 8/22/2000 | 8/24/2000 | 8/24/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 10:22:14. Contact: ###-####. under ground ok for cover 8/25/2000 7:45:44 AM
|
Electrical Rough-In | 8/11/2000 | 8/11/2000 | 8/11/2000 | P | PASS |
Pat Lass
|
|
|
###-#### bill-- unground for concrete
|
Application received | | | 7/28/2000 | | |
|
|
|
|
Issue & PRINT permit | | | 7/28/2000 | | DONE |
|
|
|
|