Final | 2/20/2001 | 2/21/2001 | 2/21/2001 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 16:09:00. Contact: ###-####.
|
DOC - Permit Finaled | 2/21/2001 | 2/21/2001 | 2/21/2001 | A | PASS |
Joe Ray
|
|
|
Added by Inspector: 404 On 2/21/2001 9:50:36 AM
|
Final | 2/14/2001 | 2/15/2001 | 2/15/2001 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/14/2001 at 15:02:24. Contact: ###-####.temporay occupancy, needs panel blanks, skirting @ bottom of panel, & floor box. 2/15/2001 11:53:32 AM
|
Electrical Rough-In | 1/16/2001 | 1/16/2001 | 1/16/2001 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 01/16/2001 at 08:53:38. Contact: ###-####. ceiling ok for cover 1/16/2001 1:54:35 PM
|
Electrical Rough-In | 12/29/2000 | 12/29/2000 | 12/29/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 12/29/2000 at 08:13:47. Contact: ###-####.
|
Electrical Rough-In | 12/28/2000 | 12/28/2000 | 12/28/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 12/28/2000 at 08:59:56. Contact: ###-####. under floor r/i 12/28/2000 1:42:24 PM
|
Rough-In Permanent Service | 12/26/2000 | 12/26/2000 | 12/26/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 12/26/2000 at 08:45:15. Contact: ###-####.
|
Electrical Rough-In | 12/26/2000 | 12/26/2000 | 12/26/2000 | P | CANC |
Joe Ray
|
|
|
Added by Inspector: 404 On 12/26/2000 1:14:30 PM
|
Electrical Rough-In | 12/18/2000 | 12/18/2000 | 12/18/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 12/18/2000 at 08:43:28. Contact: ###-####.
|
Electrical Rough-In | 12/19/2000 | 12/18/2000 | 12/18/2000 | P | PASS |
Joe Ray
|
|
|
Added by Inspector: 404 On 12/19/2000 7:45:17 AM r/i walls only ok for cover
|
Application received | | | 12/15/2000 | | |
|
|
|
|
Issue & PRINT permit | | | 12/15/2000 | | DONE |
|
|
|
|