Final | 7/2/2002 | 7/3/2002 | 7/3/2002 | A | PASS |
Mike Kinnear
|
|
|
RENE ###-#### ok final 7/3/2002 9:11:17 AM
|
DOC - Permit Finaled | 7/3/2002 | 7/3/2002 | 7/3/2002 | A | PASS |
Mike Kinnear
|
|
|
Finaled by inspector at 7/3/2002 9:11:19 AM
|
Electrical Rough-In | 2/15/2002 | 2/19/2002 | 2/19/2002 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 02/15/2002 at 14:49:24. Contact: . ok cover partunderground transformer area ok ground grid cover same area 2/19/2002 9:37:52 AM
|
Electrical Rough-In | 1/31/2002 | 1/31/2002 | 1/31/2002 | P | PART |
Mike Kinnear
|
|
|
DEEON ###-#### ###-#### ok cover underground duct bank for transformers 1/31/2002 3:24:32 PM
|
ELE-Aging Inspection | 1/28/2002 | 1/28/2002 | 1/28/2002 | | NR |
Mike Kinnear
|
|
|
suc 1/28/2002 8:05:11 AM
|
Electrical Rough-In | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | PART |
Mike Kinnear
|
|
|
COVER UP UNDER-GROUND DEON ###-#### ok cover underground marked on print 11/27/2001 10:24:57 AM
|
Rough-In Permanent Service | 11/7/2001 | 11/7/2001 | 11/7/2001 | P | PART |
Jack Frank
|
|
|
###-#### DION UNDERGROUND PARTIAL inspected 2 locations noted it on prints 11/7/2001 2:53:41 PM
|
Electrical Rough-In | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | PART |
Mike Kinnear
|
|
|
###-#### DEEON ok cover part underground conduit 11/2/2001 10:20:11 AM
|
Electrical Rough-In | 10/30/2001 | 10/30/2001 | 10/30/2001 | P | PART |
Mike Kinnear
|
|
|
###-#### DION ok grounding grid A & B level B part site lighting under ground ok cover 10/30/2001 3:21:09 PM
|
Application received | | | 10/10/2001 | | |
|
|
|
|
Issue & PRINT permit | | | 10/10/2001 | | DONE |
|
|
|
|