First Notice | 9/26/2005 | 9/26/2005 | 9/28/2005 | | DONE |
Mike Kinnear
|
|
|
This permit finaled on the web by Dan Mitchell
|
Final | 9/22/2005 | 9/26/2005 | 9/26/2005 | A | PASS |
Mike Kinnear
|
|
|
install new 3-phase 480-volt circuit from MC center to strand meter machine. see Brian Smith on-site at the Trus-Joist Research Facility. check in at the southwest corner of the building to sign in. You will be required to have a hard hat and safety glasses and steel toed shoes to enter the facility. Brian can show you the location of the work. Thanks!! -Mark-; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell ok final
|
Application received | | | 9/22/2005 | | DONE |
|
|
|
This permit was created on the web by Dan Mitchell
|