Third Notice ELE | 10/10/2006 | 10/10/2006 | 10/25/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice ELE | 9/13/2006 | 9/13/2006 | 10/10/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/30/2006 | 8/30/2006 | 9/13/2006 | | DONE |
Mike Kinnear
|
|
|
|
Final | 8/29/2006 | 8/30/2006 | 8/30/2006 | A | PASS |
Mike Kinnear
|
|
|
NEED FINAL INSPECTION ON BUILDING CORE. THANK YOU.; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH ok final note service not complete they to remove water sprinkle back flow devise in from of main switch & bring dirt leave up for proper disconnect switch height 6ft 7inch center switch nec404.8 delbert said this will be takin care of.
|
Final | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PART |
Mike Kinnear
|
|
|
need final on shell of building. thank you.; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH made appointment for 8/30/06 am
|
ELE-Aging Inspection | 8/14/2006 | 8/14/2006 | 8/14/2006 | | NR |
Mike Kinnear
|
|
|
drove job not ready
|
Permanent Service | 6/12/2006 | 6/14/2006 | 6/14/2006 | A | PASS |
Mike Kinnear
|
|
|
delbert; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley p/s u/g reconnect n ok
|
Electrical Rough-In | 6/9/2006 | 6/12/2006 | 6/12/2006 | A | PASS |
Mike Kinnear
|
|
|
UNDERGROUND ROUGH-IN FOR TRAFFIC LOOP AND READER BOARD FOR DRIVE THRU. THANK YOU. Internet Inspection Request from: BRIAN KEITH ok cover under ground conduit for reader board
|
Conference | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | PASS |
Mike Kinnear
|
|
|
delbert; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles conf regarding service
|
Conference | 5/31/2006 | 5/31/2006 | 5/31/2006 | P | PASS |
Mike Kinnear
|
|
|
delbert; Phone #: ###-#### Note: please call 1/2 hr prior Internet Inspection Request from: Cathy Chiles ok conf. with delbert
|
Application received | | | 3/23/2006 | | |
|
|
|
|
Issue permit | | | 3/23/2006 | | DONE |
|
|
|
|