Third Notice ELE | 5/23/2008 | 5/23/2008 | 6/13/2008 | | DONE |
Patricia Smith
|
|
|
This permit finaled on the web by Daniel Gamboa
|
Second Notice ELE | 5/7/2008 | 5/7/2008 | 5/23/2008 | | DONE |
Patricia Smith
|
|
|
First Notice has not been responded to.
|
First Notice | 4/15/2008 | 4/15/2008 | 5/7/2008 | | DONE |
Mike Kinnear
|
|
|
|
Final | 4/11/2008 | 4/15/2008 | 4/15/2008 | A | PASS |
Mike Kinnear
|
|
|
this is for final inspection, use Rick with GUHO Corp as contact at front desk. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa ok final
|
Final | 4/10/2008 | 4/11/2008 | 4/11/2008 | A | CANC |
Mike Kinnear
|
|
|
Use Rick Grajcar with Guho Construction as a contact at the front desk. Thank you Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa Inspection cancelled from web by: Daniel Gamboa
|
Electrical Rough-In | 3/17/2008 | 3/18/2008 | 3/18/2008 | A | PASS |
Mike Kinnear
|
|
|
Please call Gene 30 mins before inspection. Thank you. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa ok cover ceiling only
|
Electrical Rough-In | 2/29/2008 | 3/3/2008 | 3/3/2008 | A | PASS |
Bob Reichert
|
|
|
Please call Craig with Alliance to meet at front desk to gain access to building. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa ok to cover walls only, looked at u/g, ok, talked about drip shield over panel for fire piping up high
|
Electrical Rough-In | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | CANC |
William E Thomas
|
|
|
Electrical inspection for walls. Call Craig at ###-#### with any questions. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa
|
Application received | | | 2/27/2008 | | DONE |
|
|
|
This permit was created on the web by Daniel Gamboa
|