First Notice | 5/4/2009 | 5/4/2009 | 7/28/2009 | | DONE |
Pat Lass
|
|
|
|
Final | 5/4/2009 | 5/4/2009 | 5/4/2009 | A | PASS |
Pat Lass
|
|
|
Phone #: ###-#### Internet Inspection Request from: Celinda Winters
|
Electrical Rough-In | 4/9/2009 | 4/9/2009 | 4/9/2009 | P | PASS |
Jack Frank
|
|
|
Ceiling grid Phone #: ###-#### Internet Inspection Request from: Celinda Winters ceiling ok
|
Conference | 3/13/2009 | 3/13/2009 | 3/13/2009 | A | DONE |
Mike Kinnear
|
|
|
jeff ###-#### t/w jeff regarding service this shall be handled like an apt. building all meters will be in for final inspection
|
Permanent Service | 3/9/2009 | 3/9/2009 | 3/9/2009 | P | PASS |
Pat Lass
|
|
|
for permanent power Phone #: ###-#### Internet Inspection Request from: Celinda Winters P/S U/G N Ok
|
Electrical Rough-In | 2/16/2009 | 2/17/2009 | 2/17/2009 | A | PASS |
Mike Kinnear
|
|
|
underground conduit for septic pump Phone #: ###-#### Internet Inspection Request from: Celinda Winters ok cover under ground conduit & all walls ok for cover
|
Electrical Rough-In | 2/12/2009 | 2/13/2009 | 2/13/2009 | P | PART |
Jack Frank
|
|
|
Wall Rough-in Phone #: ###-#### Internet Inspection Request from: Celinda Winters all walls ok
|
Conference | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | DONE |
Mike Kinnear
|
|
|
Mike said he would come out and consult on installing the sewer pump - we would like that conultation while he is out there inspecting the other two inspections we have requested. Thank you Phone #: ###-#### Internet Inspection Request from: Celinda Winters went over sel offs for sewer lift pumps
|
Electrical Rough-In | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | CANC |
Mike Kinnear
|
|
|
underground Phone #: ###-#### Internet Inspection Request from: Celinda Winters inspection not needed (ipco conduit)
|
Application received | | | 1/21/2009 | | |
|
|
|
|
Issue permit | | | 1/21/2009 | | DONE |
|
|
|
|