Final | 11/13/2009 | 11/16/2009 | 11/16/2009 | P | PASS |
Doug A Poedy
|
|
|
CHARLIE Phone #: ###-####. ok final.
|
DOC - Permit Finaled | 11/16/2009 | 11/16/2009 | 11/16/2009 | P | PASS |
Doug A Poedy
|
|
|
|
Rough-In Permanent Service | 3/2/2009 | 3/4/2009 | 3/4/2009 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 3/2/2009 at 5:46:55 PM. Contact: ###-####. ok cover 1st & 2nd floor ri p/s o/h reconnect ok note no esc permit in project
|
Electrical Rough-In | 3/2/2009 | 3/4/2009 | 3/4/2009 | P | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 3/2/2009 at 5:45:45 PM. Contact: ###-####. wrong type inspection
|
Permanent Service | 2/27/2009 | 3/2/2009 | 3/2/2009 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 2/27/2009 at 7:16:05 AM. conference only ok
|
Electrical Rough-In | 2/27/2009 | 3/2/2009 | 3/2/2009 | P | FAIL |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 2/27/2009 at 7:14:04 AM. Contact: ###-####. replace 2 gang boxes that are damaged, 110.3(A), shall not use 2 big conn. back of panel for cables 312.5, addoutlets for wall space, 210.52(A), nail plates and 11/4" 300.4, 250.48 grd metal boxes , 314.16 check box fill
|
Conference | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | DONE |
Jack Frank
|
|
|
tom Phone #: ###-#### called answered contr questions of what is required for clearence for p/s drop gave NEC 230.9 and 230-.24, his other question had to do with ID Power requirements I told him I could help him, I inspect to NEC
|
Application received | | | 2/17/2009 | | |
|
|
|
|
Issue permit | | | 2/17/2009 | | DONE |
|
|
|
|