First Notice | 8/6/2010 | 8/6/2010 | 1/10/2011 | | DONE |
Jack Frank
|
|
|
This permit finaled on the web by Brad Baker
|
Final | 8/5/2010 | 8/6/2010 | 8/6/2010 | A | PASS |
Jack Frank
|
|
|
The project is ready for a final, thank you Phone #: ###-#### >> Inspection requested via web by Brad Baker
|
Electrical Rough-In | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | PASS |
Doug A Poedy
|
|
|
1-new wall ready for cover inspection please call for direction Thank you Phone #: ###-#### >> Inspection requested via web by Brad Baker. Phase 5 wall ok to cover.
|
Electrical Rough-In | 7/15/2010 | 7/16/2010 | 7/16/2010 | A | PASS |
Doug A Poedy
|
|
|
another section and the lobby are ready for inspection to cover ceilings thank you Phone #: ###-#### >> Inspection requested via web by Brad Baker
|
Electrical Rough-In | 6/28/2010 | 6/29/2010 | 6/29/2010 | A | PASS |
Jack Frank
|
|
|
A section of ceiling in phase 3 is ready for inspection to cover thank you Inspection requested from web by: Brad Baker Phone #: ###-#### ok
|
Electrical Rough-In | 6/18/2010 | 6/21/2010 | 6/21/2010 | A | PART |
Doug A Poedy
|
|
|
another wall section in phase 3 is ready for cover inspection thank you Inspection requested from web by: Brad Baker Phone #: ###-####
|
Electrical Rough-In | 6/10/2010 | 6/11/2010 | 6/11/2010 | A | PART |
Doug A Poedy
|
|
|
Another section of wall is ready for cover inspection Thank you Inspection requested from web by: Brad Baker Phone #: ###-####
|
Electrical Rough-In | 6/4/2010 | 6/4/2010 | 6/4/2010 | P | PASS |
Doug A Poedy
|
|
|
Good morning Jack phase 2 has a small section of grid ceiling that will be ready for inspection this afternoon so they can install tile on Monday thank you Inspection requested from web by: Brad Baker Phone #: ###-####.
|
Final | 6/4/2010 | 6/4/2010 | 6/4/2010 | P | PART |
Doug A Poedy
|
|
|
Good morning Jack phase 2 has a small section of grid ceiling that will be ready for inspection this afternoon so they can install tile on Monday thank you Inspection requested from web by: Brad Baker Phone #: ###-####. Front section.
|
Final | 5/26/2010 | 5/26/2010 | 5/26/2010 | P | CANC |
Jack Frank
|
|
|
phase 2 request for cover inspection center of room framed in area Inspection requested from web by: Brad Baker Phone #: ###-####
|
Electrical Rough-In | 5/26/2010 | 5/26/2010 | 5/26/2010 | P | PASS |
Jack Frank
|
|
|
phase 2 request for cover inspection center of room framed in area Inspection requested from web by: Brad Baker Phone #: ###-#### walls
|
Electrical Rough-In | 5/14/2010 | 5/14/2010 | 5/14/2010 | P | PASS |
Jack Frank
|
|
|
requesting an inspection for phase one lounge ceiling so the GC can lay in tile Inspection requested from web by: Brad Baker Phone #: ###-####
|
Electrical Rough-In | 5/5/2010 | 5/6/2010 | 5/6/2010 | A | PART |
Doug A Poedy
|
|
|
phase 1 new walls ready for cover Inspection requested from web by: Brad Baker Phone #: ###-####
|
Owner Supplied Equipment | | | 5/5/2010 | | |
|
|
|
|
Application received | | | 5/5/2010 | | DONE |
|
|
|
This permit was created on the web by Brad Baker
|