Final | 7/30/2010 | 7/30/2010 | 7/30/2010 | P | PASS |
Doug A Poedy
|
|
|
|
Permanent Service | 7/30/2010 | 7/30/2010 | 7/30/2010 | P | PASS |
Doug A Poedy
|
|
|
P/S O/H Connect ok.
|
Final | 7/29/2010 | 7/30/2010 | 7/30/2010 | A | FAIL |
Bob Reichert
|
|
|
Phone #: ###-#### >> Inspection requested via web by Neal Rumsey called, left message, left correction notice, NEC 230.24(A) shall provide 8' clearance over roof surface for service conductors, 250.53(G) upper end of electrodes shall be flush with or below ground, 408.4 shall complete circuit schedules, note; corrections shall be made within 5 working days, advised that contractor shall call for p/s inspection
|
Final | 7/28/2010 | 7/29/2010 | 7/29/2010 | A | FAIL |
Doug A Poedy
|
|
|
Phone #: ###-#### >> Inspection requested via web by Neal Rumsey. Needs to have a 2" mast per Idaho power.
|
Application received | | | 7/28/2010 | | DONE |
|
|
|
This permit was created on the web by Neal Rumsey
|
First Notice | 7/30/2010 | 7/30/2010 | | | |
Doug A Poedy
|
|
|
|