First Notice | 6/12/2012 | 6/12/2012 | 9/15/2014 | | DONE |
Daryl DeGrange
|
|
|
|
Final | 6/12/2012 | 6/12/2012 | 6/12/2012 | P | PASS |
Daryl DeGrange
|
|
|
Please contact Mike at ###-#### to schedule a time to meet you at the job site. Please contact us at least one hour before. Thank you Phone #: ###-#### >> Inspection requested via web by Sue Minick final ok
|
Final | 6/8/2012 | 6/12/2012 | 6/12/2012 | A | NH |
Daryl DeGrange
|
|
|
final at Good Street pump station Phone #: ###-#### >> Inspection requested via web by Sue Minick
|
Rough-In Permanent Service | 3/29/2012 | 3/29/2012 | 3/29/2012 | P | PASS |
Daryl DeGrange
|
|
|
We would like to get power back on for this afternoon Dean is on site connceting the new service. We should be ready by 1-2:00 but if you could call first that would be good Mike ###-####. Phone #: ###-#### >> Inspection requested via web by Mike TenHulzen p/s u/g n ok
|
Electrical Rough-In | 2/8/2012 | 2/8/2012 | 2/8/2012 | P | PASS |
Daryl DeGrange
|
|
|
We need permission for ceiling installation Phone #: ###-#### >> Inspection requested via web by Lori Stout rough-in ok cover hard lid
|
Electrical Rough-In | 12/1/2011 | 12/2/2011 | 12/2/2011 | A | PASS |
Daryl DeGrange
|
|
|
INSPECTION FOR THE UNDERGROUND N THE PUMP STATION AND TO A PRV VAULT. MORE UNDERGROUNG TO FOLLOW BUT THE OCNTRACTOR IS TRYING TO POUR THE FLOOR AREA. PLEASE LET ME KNOW IF THERE ARE ANY QUESTIONS. Phone #: ###-#### >> Inspection requested via web by Mike TenHulzen rough-in ok cover underground from eastside of building foundation west. piping not complete on eastside at this time.
|
Issue PAID IN FULL permit | | | 12/1/2011 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/1/2011 | | DONE |
|
|
|
This permit was created on the web by Lori Stout
|