Final | 4/4/2012 | 4/6/2012 | 4/6/2012 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by George Pascua final ok
|
Electrical Rough-In | 3/5/2012 | 3/5/2012 | 3/5/2012 | P | PASS |
Bob Reichert
|
|
|
Floor Heat Phone #: ###-#### >> Inspection requested via web by George Pascua corrections made, ok cover floor heat
|
Electrical Rough-In | 3/2/2012 | 3/5/2012 | 3/5/2012 | A | FAIL |
Bob Reichert
|
|
|
Need Floor Heat inspection Phone #: ###-#### >> Inspection requested via web by George Pascua called contractor and told that they must install and per instructions
|
Electrical Rough-In | 2/24/2012 | 2/27/2012 | 2/27/2012 | A | PART |
Jack Frank
|
|
|
george Phone #: ###-#### walls ceiling ok no floor heat installed
|
Issue PAID IN FULL permit | | | 2/24/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/24/2012 | | DONE |
|
|
|
This permit was created on the web by George Pascua
|