Final | 4/1/2013 | 4/1/2013 | 4/1/2013 | A | PASS |
Bob Reichert
|
|
|
Please call first to ensure homeowner is available. Thank You Phone #: ###-#### >> Inspection requested via web by Eric Brown ok final
|
Electrical Rough-In | 3/12/2013 | 3/12/2013 | 3/12/2013 | P | PASS |
Bob Reichert
|
|
|
Floor heat inspection in master bath. Will be ready right before lunch. Please call to schedule someone to meet. Thank you Phone #: ###-#### >> Inspection requested via web by Eric Brown ok cover floor heat
|
Electrical Rough-In | 2/12/2013 | 2/12/2013 | 2/12/2013 | P | PASS |
Bob Reichert
|
|
|
Please call to ensure access Phone #: ###-#### >> Inspection requested via web by Eric Brown ri ok, do floor heat later
|
Issue PAID IN FULL permit | | | 2/12/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/12/2013 | | DONE |
|
|
|
This permit was created on the web by Eric Brown
|