First Notice | 11/6/2013 | 11/6/2013 | 1/15/2018 | | DONE |
Bob Reichert
|
|
|
This permit finaled on the web by David Mackey
|
Final | 11/6/2013 | 11/6/2013 | 11/6/2013 | P | PASS |
Bob Reichert
|
|
|
Please final. Call Dave in advance to meet you at job site. As much advance notice as possible, driving from Emmett Phone #: ###-#### >> Inspection requested via web by David Mackey ok cover ceiling, ok final, signed card
|
Rough-In Permanent Service | 9/17/2013 | 9/17/2013 | 9/17/2013 | A | PASS |
Bob Reichert
|
|
|
request rough-in/wall cover for all walls to 10'' and bathroom ceilings. All other areas are drop ceiling Phone #: ###-#### >> Inspection requested via web by David Mackey hard lids baths, walls ok cover, p/s u/g n ok
|
Rough-In Permanent Service | 9/16/2013 | 9/16/2013 | 9/16/2013 | P | NR |
Bob Reichert
|
|
|
rough-in inspection and permanent service inspection. Electricians will be at job-site until mid afternoon. Call Carlos for any questions at ###-#### Phone #: ###-#### >> Inspection requested via web by David Mackey met electrician, asked to recall for am, still wiring switches and receptacles, needs nailplates, strapping
|
Rough-In Permanent Service | 7/31/2013 | 7/31/2013 | 7/31/2013 | P | PASS |
Bob Reichert
|
|
|
Please re-inspect underground Phone #: ###-#### >> Inspection requested via web by David Mackey corrections made, ok cover u/g for slab only
|
Electrical Rough-In | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | FAIL |
Bob Reichert
|
|
|
We are requesting an underground inspection for conduit work under the slab. Phone #: ###-#### >> Inspection requested via web by David Mackey called, shall maintain spacing for u/g raceways
|
Issue PAID IN FULL permit | | | 7/30/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/30/2013 | | DONE |
|
|
|
This permit was created on the web by David Mackey
|