First Notice | 1/10/2014 | 1/10/2014 | 1/29/2014 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Sean DeLacy
|
Final | 1/10/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Rock A. Hudson
|
|
|
Final. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen Final ok
|
Electrical Rough-In | 12/12/2013 | 12/12/2013 | 12/12/2013 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling Cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen 13th floor ceiling ok leave tile out for exit and emergency. Rough in ok cover
|
Electrical Rough-In | 12/10/2013 | 12/10/2013 | 12/10/2013 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen All offices except north west corner and common areas, All borders rough in ok cover
|
Electrical Rough-In | 11/12/2013 | 11/12/2013 | 11/12/2013 | A | PASS |
Rock A. Hudson
|
|
|
Ceiling cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen 13th floor hard lid east of elevator lobby rough in ok cover
|
Electrical Rough-In | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | PASS |
Rock A. Hudson
|
|
|
13th Floor lobby ceiling cover. Danny is on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen 13th floor elevator lobby ceiling rough in ok cover
|
Electrical Rough-In | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Rock A. Hudson
|
|
|
Danny. Wall Cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy office wall rough in complete ok cover
|
Electrical Rough-In | 10/7/2013 | 10/7/2013 | 10/7/2013 | A | PASS |
Rock A. Hudson
|
|
|
wall cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen Offices 157 and 158 wall rough in ok cover
|
Electrical Rough-In | 10/1/2013 | 10/2/2013 | 10/2/2013 | A | PASS |
Rock A. Hudson
|
|
|
Wall cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen Outer office walls for corridor, North, south, and west Interior office wall rough in ok cover
|
Electrical Rough-In | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | PASS |
Rock A. Hudson
|
|
|
wall cover. Danny on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen Offices107 thru113 and 125 thru 135 wall rough in inside only ok
|
Electrical Rough-In | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | PASS |
Rock A. Hudson
|
|
|
Wall Cover. Danny is on site Phone #: ###-#### >> Inspection requested via web by Buster Bowen offices 114 thru 124 wall rough in ok cover
|
Issue PAID IN FULL permit | | | 9/16/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/16/2013 | | DONE |
|
|
|
This permit was created on the web by Buster Bowen
|