Final | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | PASS |
Rex Boyles
|
|
|
Please call Byron with any problems Phone #: ###-#### >> Inspection requested via web by Rhonda Zamagni final ok corrections made
|
Final | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | FAIL |
Rock A. Hudson
|
|
|
Disconnecting means shall be provided for all hard wired appliances. Main disconnects shall be identified as to their purpose. 2-pole 20 as well. Disposal receptical shall have cover. Inspection request called in on temp pole permit. No phone number listed
|
Electrical Rough-In | 3/21/2014 | 3/24/2014 | 3/24/2014 | A | PASS |
Rex Boyles
|
|
|
Inspection for radiant heat flooring in master bathroom and guest bathroom. Thank you, >> Inspection requested via web by Rhonda Zamagni ok to cover both bathrooms floor heat
|
Electrical Rough-In | 1/15/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Rock A. Hudson
|
|
|
Please contact Dick ###-#### or Byron at ###-#### so one of them can do a walk through with the inspector. >> Inspection requested via web by Rhonda Zamagni Solar to be permitted and installed by others. House and garage rough in ok cover
|
Permanent Service | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Rock A. Hudson
|
|
|
Please contact Dick ###-#### or Byron at ###-#### so one of them can do a walk through with the inspector. >> Inspection requested via web by Rhonda Zamagni p/s u/g n ok
|
Electrical Rough-In | 1/15/2014 | 1/15/2014 | 1/15/2014 | P | FAIL |
Rock A. Hudson
|
|
|
>> Inspection requested via web by Rhonda Zamagni 300.4- NM cable shall be protected where ran through bored hole that is less than 1 1/4" from framing surface. 300.4- Raceways containing conductors larger than #4 shall have bushing where they enter box. 250.32(A)- A seperate structure supplied by feeders or branch circuits shall have a grounding electrode system installed. 250.32(B)- For a grounded system at the seperate structure an equptment grounding conductor as described in 250.118 shall be run with the supply conductors and be connected at disconnecting means and grounding electrode. Increase room count on permit to 14 rooms. No number provided to contact contractor. Ok to foam seal
|
Rough-In Permanent Service | 10/18/2013 | 10/21/2013 | 10/21/2013 | A | PASS |
Rock A. Hudson
|
|
|
Check the trench of the conduit so we can cover. Please call Byron with any questions Phone #: ###-#### >> Inspection requested via web by Rhonda Zamagni Service not ready. Underground under slab and between buildings rough in ok cover
|
Issue PAID IN FULL permit | | | 10/10/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/10/2013 | | DONE |
|
|
|
This permit was created on the web by Rhonda Zamagni
|