DOC - Permit Finaled | | | 10/19/2015 | | DONE |
|
|
|
|
Change Status to I | | | 5/28/2015 | | DONE |
Christina Prado
|
|
|
Permit reopened to allow for all remaining work & inspections to be completed for Aeration Basin #6. Permit was closed out without this portion being started resulting in an invalid Fincal Cerificate of Occuppancy granted. Permit status changed to TMP to allow for occupancy on completed portions. Scope of work was also updated to show a more accurate description of all work performed under this BLD//cdp
|
Final | 4/30/2015 | 4/30/2015 | 4/30/2015 | P | PASS |
Rex Boyles
|
|
|
Final not temp closing out permit pulling new one for the rest of the job Phone #: ###-#### Inspection requested via web by matt miller corrections made final ok
|
Final | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PART |
Rock A. Hudson
|
|
|
Final the thk bldg Phone #: ###-#### Inspection requested via web by matt miller Some valuation on this permit covers work in other areas. New permit to be pulled for other work. Temp final ok
|
Electrical Rough-In | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | PASS |
Rock A. Hudson
|
|
|
Entry and restroom ceiling cover Phone #: ###-#### Inspection requested via web by matt miller Did prelimary walk through building, disconnecting means for misc equipment above 6'7" will relocate. Grid rough in ok cover
|
Electrical Rough-In | 4/3/2015 | 4/6/2015 | 4/6/2015 | A | PASS |
Rock A. Hudson
|
|
|
basin 5,ras bldg, wsr tank, daft building. Phone #: ###-#### Inspection requested via web by matt miller Areas noted conuits bonds needed in bldg #5 rough in ok
|
Permanent Service | 2/3/2015 | 2/3/2015 | 2/3/2015 | A | PASS |
Rock A. Hudson
|
|
|
Ras service Phone #: ###-#### Inspection requested via web by matt miller p/s u/g n ok
|
Permanent Service | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | FAIL |
Rock A. Hudson
|
|
|
Ras bldg service Phone #: ###-#### Inspection requested via web by matt miller 110.26(C)(3)- Where equiptment rated 1200A or more that contain overcurrent devices personnel door shall have panic hardware.
|
Permanent Service | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | NH |
Rock A. Hudson
|
|
|
Ras service Phone #: ###-#### Inspection requested via web by matt miller No return phone call. Not sure where service is located on premisis
|
Electrical Rough-In | 1/23/2015 | 1/26/2015 | 1/26/2015 | A | PART |
Rock A. Hudson
|
|
|
Wsr tank under ground Phone #: ###-#### Inspection requested via web by matt miller Under ground rough in ok as noted. Check grounding electode system and panic hardware on door of vault.
|
Electrical Rough-In | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PASS |
Rock A. Hudson
|
|
|
Underground Ras secondary, wall the bldg bathroom lids Phone #: ###-#### Inspection requested via web by matt miller RAS underground, Bathroom hardlids, and upstairs dividing wall rough in ok cover
|
Permanent Service | 12/30/2014 | 12/31/2014 | 12/31/2014 | A | PASS |
Rock A. Hudson
|
|
|
The best service Phone #: ###-#### Inspection requested via web by matt miller Performance test complete. p/s u/g n ok
|
Electrical Rough-In | 12/31/2014 | 12/31/2014 | 12/31/2014 | P | PASS |
Rock A. Hudson
|
|
|
The best service Phone #: ###-#### Inspection requested via web by matt miller WSR underground rough in ok cover
|
Electrical Rough-In | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | PASS |
Rock A. Hudson
|
|
|
Entry bathroom walls Phone #: ###-#### Inspection requested via web by matt miller Rough in ok cover
|
Electrical Rough-In | 12/16/2014 | 12/16/2014 | 12/16/2014 | A | PASS |
Rock A. Hudson
|
|
|
Electrical room ceiling Phone #: ###-#### Inspection requested via web by matt miller Electrical room hard lid rough in ok cover
|
Electrical Rough-In | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Rock A. Hudson
|
|
|
Transformer secondary underground Phone #: ###-#### Inspection requested via web by matt miller Secondaries south west corner rough in ok cover
|
Electrical Rough-In | 12/2/2014 | 12/2/2014 | 12/2/2014 | P | PASS |
Rock A. Hudson
|
|
|
Underground wsr tank and thk primarys Phone #: ###-#### Inspection requested via web by matt miller underground listed rough in ok cover
|
Electrical Rough-In | 10/28/2014 | 10/29/2014 | 10/29/2014 | A | PASS |
Rock A. Hudson
|
|
|
Bathroom underground Phone #: ###-#### Inspection requested via web by matt miller Bathroom and small pad N.E. corner underground rough in ok cover
|
Electrical Rough-In | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Rock A. Hudson
|
|
|
Wall 14 Phone #: ###-#### Inspection requested via web by matt miller Wall 14 rough in ok cover
|
Electrical Rough-In | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | PASS |
Daryl DeGrange
|
|
|
Under ground east side thickener building Phone #: ###-#### Inspection requested via web by matt miller Rough-in ok cover from building to vault
|
Electrical Rough-In | 9/27/2014 | 9/29/2014 | 9/29/2014 | A | PASS |
Daryl DeGrange
|
|
|
last wall on wsr tank Phone #: ###-#### Inspection requested via web by matt miller rough-in ok cover wall #8
|
Electrical Rough-In | 9/9/2014 | 9/10/2014 | 9/10/2014 | A | PASS |
Daryl DeGrange
|
|
|
wsr tank wall 7 Phone #: ###-#### Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PASS |
Daryl DeGrange
|
|
|
wsr tank wall 6 Phone #: ###-#### Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | PASS |
Daryl DeGrange
|
|
|
WSR Tank Southeast and Northeast wall pours. Onsite - Joe Davis @ ###-#### Phone #: ###-#### Inspection requested via web by Todd Alder rough-in ok cover two conduits in those walls
|
Electrical Rough-In | 7/23/2014 | 7/23/2014 | 7/23/2014 | P | PASS |
Daryl DeGrange
|
|
|
pipe in boxes in wall 31 and 32 Phone #: ###-#### >> Inspection requested via web by matt miller Rough-in ok cover walls 31 and 32
|
Electrical Rough-In | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Daryl DeGrange
|
|
|
two walls on upper deck Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover walls 24 and 28
|
Change Status to I | | | 7/15/2014 | | DONE |
Christina Prado
|
|
|
last inspection 7/10/14 was r/i only not final, see notes in inspection
|
Final | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PASS |
Daryl DeGrange
|
|
|
thickener tank slab southeast corner Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok pour
|
Electrical Rough-In | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | PASS |
Daryl DeGrange
|
|
|
conduit in wall 29 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | PASS |
Daryl DeGrange
|
|
|
pipe in wall 30 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | PASS |
Rock A. Hudson
|
|
|
pipe and boxes in wall 27 Phone #: ###-#### >> Inspection requested via web by matt miller North 3rd of wall 27 pour rough in ok cover
|
Electrical Rough-In | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PASS |
Daryl DeGrange
|
|
|
wall 25 pipe and boxes Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 6/11/2014 | 6/11/2014 | 6/11/2014 | P | PASS |
Daryl DeGrange
|
|
|
wall 29 outlets and switches Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok pour
|
Electrical Rough-In | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PASS |
Daryl DeGrange
|
|
|
polymer room underground Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Daryl DeGrange
|
|
|
thickener bldg. electrical room underground Phone #: ###-#### >> Inspection requested via web by matt miller Rough-in ok cover/pour underground electrical room
|
Electrical Rough-In | 4/7/2014 | 4/7/2014 | 4/7/2014 | P | PASS |
Daryl DeGrange
|
|
|
under ground pump room Phone #: ###-#### >> Inspection requested via web by matt miller Rough-in ok cover/pour
|
Electrical Rough-In | 4/3/2014 | 4/3/2014 | 4/3/2014 | A | PASS |
Rex Boyles
|
|
|
Electrical and polymer room walls
Phone #: ###-#### >> Inspection requested via web by matt miller rough in ok in electrical room and polymer room walls ok to pour
|
Electrical Rough-In | 3/27/2014 | 3/27/2014 | 3/27/2014 | P | PASS |
Daryl DeGrange
|
|
|
fermentation tank deck pour #2 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 3/19/2014 | 3/20/2014 | 3/20/2014 | A | PASS |
Daryl DeGrange
|
|
|
duct bank to utilidor. Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover duct bank
|
Electrical Rough-In | 3/11/2014 | 3/12/2014 | 3/12/2014 | A | PASS |
Daryl DeGrange
|
|
|
wall 9 pipe and fermentation tank conduit in deck Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 3/6/2014 | 3/6/2014 | 3/6/2014 | P | PASS |
Daryl DeGrange
|
|
|
pipes and boxes and sleeves in wall 16 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 2/27/2014 | 2/27/2014 | 2/27/2014 | P | CANC |
Daryl DeGrange
|
|
|
wall 12 conduit and box Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 2/20/2014 | 2/20/2014 | 2/20/2014 | P | PASS |
Daryl DeGrange
|
|
|
wall 20 outlets and blockouts Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Electrical Rough-In | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Daryl DeGrange
|
|
|
duct bank from thickener bldg to transformer flt-tx-1 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok cover
|
Change Status to I | | | 2/13/2014 | | |
|
|
|
last inspection was r/i not final per 445
|
Final | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PASS |
Daryl DeGrange
|
|
|
wall 18 Phone #: ###-#### >> Inspection requested via web by matt miller rough-in ok pour wall #18
|
Electrical Rough-In | 2/11/2014 | 2/11/2014 | 2/11/2014 | P | PASS |
Daryl DeGrange
|
|
|
wall on north side with form on it Phone #: ###-#### >> Inspection requested via web by matt miller Rough-in ok cover north wall # 10
|
Electrical Rough-In | 1/28/2014 | 1/30/2014 | 1/30/2014 | P | PASS |
Daryl DeGrange
|
|
|
Cover inspection for next wall pour at new Thickener Building. Phone #: ###-#### >> Inspection requested via web by Todd Alder rough-in ok cover
|
Electrical Rough-In | 1/27/2014 | 1/27/2014 | 1/27/2014 | P | PASS |
Rock A. Hudson
|
|
|
Inspection of conduits in wall pour of new Thickener Building Phone #: ###-#### >> Inspection requested via web by Todd Alder Interior entry wall pour marked on contractors print rough in ok cover
|
Electrical Rough-In | 12/13/2013 | 12/16/2013 | 12/16/2013 | P | PASS |
Daryl DeGrange
|
|
|
Inspection of underground conduits. Matt Miller is onsite superintendent. Phone #: ###-#### >> Inspection requested via web by Todd Alder rough-in ok cover underground electrical room under footings
|
Electrical Rough-In | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | PASS |
Daryl DeGrange
|
|
|
Ufer ground inspection Phone #: ###-#### >> Inspection requested via web by Neil Adams rough-in ok cover Ufer grounding conductor
|
Electrical Rough-In | 11/6/2013 | 11/7/2013 | 11/7/2013 | A | PASS |
Rock A. Hudson
|
|
|
underground inspection needed under new building on south west corner of WWTP Phone #: ###-#### >> Inspection requested via web by Neil Adams 5" conduits as marked in office rough in ok cover
|
Issue PAID IN FULL permit | | | 11/6/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 11/6/2013 | | DONE |
|
|
|
This permit was created on the web by Todd Alder
|
First Notice | 4/30/2015 | 4/30/2015 | | | |
Rex Boyles
|
|
|
|
First Notice | 7/10/2014 | 7/10/2014 | | | |
Daryl DeGrange
|
|
|
|