First Notice | 11/3/2014 | 11/3/2014 | 1/23/2017 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Mike Swift
|
Final | 10/31/2014 | 11/3/2014 | 11/3/2014 | A | PASS |
Rock A. Hudson
|
|
|
Mike Phone #: ###-#### Final ok
|
Final | 10/29/2014 | 10/30/2014 | 10/31/2014 | P | CANC |
Rex Boyles
|
|
|
Mike Phone #: ###-#### will call in monday to inspect with Rock H.
|
Final | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PART |
Rock A. Hudson
|
|
|
PARTIAL FINAL ON LIGHTING Phone #: ###-#### Hanger area ok to move in equipment. Check outlets for GFCI protection on final.
|
Final | 10/2/2014 | 10/2/2014 | 10/2/2014 | P | PART |
Rock A. Hudson
|
|
|
Mike Phone #: ###-#### Ok to install office furniture and occupy when complete
|
Electrical Rough-In | 9/25/2014 | 9/26/2014 | 9/26/2014 | P | FAIL |
Rock A. Hudson
|
|
|
Shane Phone #: ###-#### 210.8- receptical outlet located within 6' of sink in rm 11 shall have GFCI protection. 422.52- Drinking fountains shall have GFCI protection. Multiple recepticals not working, rms 103, 106, 126, 213 no recept at all. Up neededs complete check
|
Electrical Rough-In | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | PASS |
Daryl DeGrange
|
|
|
Mike-2 nd floor Phone #: ###-#### rough-in ok cover ceiling grid
|
Electrical Rough-In | 8/15/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Rock A. Hudson
|
|
|
Cover inspection on 1st floor ceiling please-Mike Phone #: ###-#### 1st floor grid rough in ok cover
|
Electrical Rough-In | 8/13/2014 | 8/14/2014 | 8/14/2014 | A | PASS |
Rock A. Hudson
|
|
|
west hanger wall Phone #: ###-#### Around west door fabric wall rough in ok cover
|
Electrical Rough-In | 7/29/2014 | 7/29/2014 | 7/29/2014 | A | PASS |
Rock A. Hudson
|
|
|
Basement ceiling cover inspection Phone #: ###-#### >> Inspection requested via web by Mike Swift Basement ceiling grid rough in ok cover
|
Electrical Rough-In | 7/17/2014 | 7/17/2014 | 7/17/2014 | P | PASS |
Rock A. Hudson
|
|
|
ceiling, 2nd floor // Mike Phone #: ###-#### 2nd floor hall lower grid, Center stairway hard lid
|
Electrical Rough-In | 7/10/2014 | 7/10/2014 | 7/10/2014 | P | PASS |
Rock A. Hudson
|
|
|
Mike-1 hanger wall Phone #: ###-#### Check on next trip that 3 receptical outlets on south hanger wall are mounted 18" or higher above floor. South hanger wall rough in ok cover
|
Rough-In Permanent Service | 7/2/2014 | 7/3/2014 | 7/3/2014 | P | PASS |
Daryl DeGrange
|
|
|
mike Phone #: ###-#### permanent service only p/s u/g n ok
|
Electrical Rough-In | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Rock A. Hudson
|
|
|
Mike-over for east wall Phone #: ###-#### Hanger and avionics east wall rough in ok cover
|
Electrical Rough-In | 6/26/2014 | 6/27/2014 | 6/27/2014 | A | PASS |
Rock A. Hudson
|
|
|
under ground inspection please-terrie Phone #: ###-#### Under ground for fiber and sign rough in ok cover
|
Electrical Rough-In | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PASS |
Rock A. Hudson
|
|
|
Mike Phone #: ###-#### - rough-in/cover for mezzanine also stair wall rough in ok cover
|
Electrical Rough-In | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PASS |
Rock A. Hudson
|
|
|
2fl walls - MIke Phone #: ###-#### 2nd floor walls and hard lid rough in ok cover
|
Electrical Rough-In | 6/9/2014 | 6/9/2014 | 6/9/2014 | A | PASS |
Bob Reichert
|
|
|
stair well inspection Phone #: ###-#### >> Inspection requested via web by Mike Swift ok cover stairwells basement and 1st floor and hangar mezzanine for 10' above ceiling
|
Electrical Rough-In | 6/3/2014 | 6/4/2014 | 6/4/2014 | A | PASS |
Rock A. Hudson
|
|
|
first floor ceiling and trench in basement // Mike Phone #: ###-#### 1st floor hard lids and basement trench rough in ok cover
|
Electrical Rough-In | 5/29/2014 | 5/30/2014 | 5/30/2014 | P | PASS |
Rock A. Hudson
|
|
|
First fl walls - Mike Phone #: ###-#### 1st floor office wall rough in ok cover
|
Electrical Rough-In | 5/23/2014 | 5/27/2014 | 5/27/2014 | A | PASS |
Rock A. Hudson
|
|
|
re-inspect for partial ceiling basement Phone #: ###-#### Basement hard lid rough in ok cover
|
Electrical Rough-In | 5/23/2014 | 5/23/2014 | 5/23/2014 | P | FAIL |
Rock A. Hudson
|
|
|
partial basement ceiling - Mike Phone #: ###-#### 300.11 Hard lid support system shall not support light fixtures and boxes unless system is rated for support of additional fixtures.
|
Electrical Rough-In | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Rock A. Hudson
|
|
|
Basement walls please-Mike Phone #: ###-#### Told not to allow 1 siding walls prior to inspection. Basement walls only rough in ok cover.
|
Electrical Rough-In | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PART |
Rock A. Hudson
|
|
|
for the basement only // Mike Phone #: ###-#### Basement perimeter walls rough in ok cover
|
Electrical Rough-In | 3/7/2014 | 3/7/2014 | 3/7/2014 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Mechanical bath in existing hanger rough in ok cover
|
Issue PAID IN FULL permit | | | 12/23/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/23/2013 | | DONE |
|
|
|
This permit was created on the web by Mike Swift
|