Final | 10/14/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Rock A. Hudson
|
|
|
I will meet you at project as per our phone call the other day. early on the 16th.
Thanks
Mike Cole B ; B Electric ###-#### Phone #: ###-#### Inspection requested via web by Mike Cole Final ok
|
Electrical Rough-In | 10/16/2014 | 10/16/2014 | 10/16/2014 | P | PASS |
Rock A. Hudson
|
|
|
I will meet you at project as per our phone call the other day. early on the 16th.
Thanks
Mike Cole B ; B Electric ###-#### Phone #: ###-#### Inspection requested via web by Mike Cole Rough in ok
|
Issue PAID IN FULL permit | | | 5/15/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 5/15/2014 | | |
|
|
|
|
Application received | | | 5/15/2014 | | DONE |
|
|
|
This permit was created on the web by Mike Cole
|
First Notice | 10/16/2014 | 10/16/2014 | | | |
Rock A. Hudson
|
|
|
|