Final | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PASS |
Rex Boyles
|
|
|
Please call Jesse 1/2 hr. ahead of time so he can meet the inspector on-site to go over the job. Phone #: ###-#### Inspection requested via web by Matthew Dunay final ok for roughed in solar wiring only for future.
|
Electrical Rough-In | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PASS |
Rex Boyles
|
|
|
Please call Jesse 1/2 hr. ahead of time so he can meet the inspector on-site to go over the job. Phone #: ###-#### Inspection requested via web by Matthew Dunay r/i ok future solar for 2 invertors ok
|
Issue PAID IN FULL permit | | | 10/8/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/8/2014 | | DONE |
|
|
|
This permit was created on the web by Matthew Dunay
|