First Notice | 12/29/2014 | 12/29/2014 | 1/22/2015 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Jarod Murray
|
Final | 12/24/2014 | 12/29/2014 | 12/29/2014 | P | PASS |
Rock A. Hudson
|
|
|
Rough-in and final for sub panel change out. Phone #: ###-#### Inspection requested via web by Jarod Murray Final ok
|
Electrical Rough-In | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PASS |
Rock A. Hudson
|
|
|
Rough-in and final for sub panel change out. Phone #: ###-#### Inspection requested via web by Jarod Murray Sub panel and NM cable change out rough in ok
|
Issue PAID IN FULL permit | | | 12/24/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 12/23/2014 | | DONE |
|
|
|
This permit was created on the web by Jarod Murray
|