Final | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Bob Reichert
|
|
|
20 solar panels. AC micro-inverter system. No DC voltage. Enphase M250 Micro-Inverters, that are CSA, IEEE-1547, and UL-1741 listed. Ironridge Integrated Grounding System mid clamps, bonding straps and bonding lugs. And 270 watt Suniva panels, ETL listed.
A single home run, in metal conduit, is ran from the solar array to the knife switch, located next to meter base on the front side of home next to garage. From the knife switch to breaker in sub panel mounted directly along side the knife switch. The solar breaker and the knife switch are permanently marked for solar, and the circuit numbers identified in the knife switch and on the panel schedule.
The inverters, panels and rails are all bonded with a unbroken number 6 ground that runs back to the service grounding electrode under the meter base in the main panel.
Thanks guys, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King ok final
|
Electrical Rough-In | 5/18/2015 | 5/18/2015 | 5/18/2015 | P | PASS |
Bob Reichert
|
|
|
The guys will be out today putting up the micro inverters and panels. The panels and materials will be on the ground and available for listing inspection. They should be getting there and unloading around 11:30 Thanks guys, Ryan King Phone #: ###-#### Inspection requested via web by Ryan King ri ok, looked at listings
|
Issue PAID IN FULL permit | | | 3/18/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 3/18/2015 | | |
|
|
|
|