Final | 8/25/2015 | 8/26/2015 | 8/26/2015 | A | PASS |
Rex Boyles
|
|
|
Units 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% ok rm 540 and corridors perm. occupancy ok
|
Final | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PART |
Rex Boyles
|
|
|
Unit inspections, 5th floor west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% except rm 540 and corridors
|
Final | 8/14/2015 | 8/15/2015 | 8/15/2015 | P | CANC |
Rex Boyles
|
|
|
Rafial - ###-#### finished in the AM inspection. not needed
|
Final | 8/14/2015 | 8/15/2015 | 8/15/2015 | A | PART |
Rex Boyles
|
|
|
Rafial - ###-#### still need GFCI breakers for spa and pump inspection. Temp.occupancy ok 1st floor NO SPA USAGE
|
Final | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | PART |
Rex Boyles
|
|
|
Units 3rd and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 322 and 424. Temporary occupancy ok for 2nd floor rooms and corridors and lobbys 100% complete.
|
Final | 8/14/2015 | 8/14/2015 | 8/14/2015 | A | PART |
Rex Boyles
|
|
|
Unit inspections, 3rd and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 319, 326, 322 424
|
Final | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | PART |
Rex Boyles
|
|
|
Final inspections for units. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 421 thru 423, 425 thru 432, 434 thru 442
|
Electrical Rough-In | 8/13/2015 | 8/13/2015 | 8/13/2015 | A | PASS |
Rex Boyles
|
|
|
Corridor grid ceiling inspection, 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok
|
Final | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PART |
Rex Boyles
|
|
|
Unit final inspections 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo all units inspected previously now have CFL lamps to meet 50% energy effiecient lamps, including todays inspections. All exterior receptacles on 2nd floor ok now. final ok rms. 321, 323 thru 325, 327 thru 334, 336 thru 341
|
Electrical Rough-In | 8/7/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Rex Boyles
|
|
|
Corridor ceilings 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ceilings west wing corridor ok
|
Electrical Rough-In | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | NR |
Rex Boyles
|
|
|
4th floor corridor grid ceiling inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
|
Final | 8/5/2015 | 8/5/2015 | 8/5/2015 | P | NR |
Rex Boyles
|
|
|
Final inspections units 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo dishwashers not in yet
|
Final | 8/5/2015 | 8/5/2015 | 8/5/2015 | A | PART |
Rex Boyles
|
|
|
Final inspections units 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 221, 224 thru 231, 232 thru 241. exterior receptacles not done in rms. 200, 218, 223 and 233. All rooms still need 50% energy efficient lamps.
|
Electrical Rough-In | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | PASS |
Rex Boyles
|
|
|
2nd floor t grid ceiling inspection, corridors only. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok to cover
|
Electrical Rough-In | 7/31/2015 | 7/31/2015 | 7/31/2015 | A | PASS |
Rex Boyles
|
|
|
3rd floor t grid ceiling inspection, corridors only. Phone #: ###-#### Inspection requested via web by Rafael Castillo 3rd flr corridor ceiling r/i ok
|
Electrical Rough-In | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | CANC |
Rex Boyles
|
|
|
3rd floor west corridor grid ceiling. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|
Electrical Rough-In | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | NR |
Rex Boyles
|
|
|
Grid ceiling inspection 3rd floor corridors. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
|
Conference | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | DONE |
Rex Boyles
|
|
|
Discuss location of receptacles in islands. Phone #: ###-#### Inspection requested via web by Rafael Castillo cut in receptacles under countertop instead of cabinets ok Discuss temp. occupancy status after rooms are finaled is ok per wing
|
Electrical Rough-In | 7/23/2015 | 7/23/2015 | 7/23/2015 | A | PASS |
Rex Boyles
|
|
|
5th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceiling in rm. 542
|
Electrical Rough-In | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | NR |
Rex Boyles
|
|
|
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
|
Electrical Rough-In | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Rex Boyles
|
|
|
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo R/I OK DROP CEILINGS in rms 534 thru 537, 539 and 541
|
Electrical Rough-In | 7/21/2015 | 7/21/2015 | 7/21/2015 | A | PASS |
Rex Boyles
|
|
|
Drop ceiling rough in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings rms 530 and 532
|
Electrical Rough-In | 7/15/2015 | 7/15/2015 | 7/15/2015 | A | PASS |
Rex Boyles
|
|
|
Drop ceilings 3rd floor, units 5th floor, shafts 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 301 thru 304, 332, 335, 338 and 339. r/i ok rms 532,534,535 thru 541. r/i ok vent. shafts in 402 thru 405 and 407
|
Issue PAID IN FULL permit | | | 7/10/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Owner Supplied Equipment | | | 7/10/2015 | | |
|
|
|
|
Application received | | | 7/10/2015 | | DONE |
|
|
|
This permit was created on the web by Cathy Duchek
|
Electrical Rough-In | 6/30/2015 | 6/30/2015 | 6/30/2015 | A | PASS |
Rex Boyles
|
|
|
4th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceiling rm. 419
|
Electrical Rough-In | 6/29/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Rex Boyles
|
|
|
4th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i drop ceilings in rms. 421,422,423,424 and 430
|
Electrical Rough-In | 6/26/2015 | 6/26/2015 | 6/26/2015 | A | PASS |
Rex Boyles
|
|
|
5th floor shafts, 4th floor drop ceilings, 5th floor corridors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 100% vent. shafts on 5th flr., rm. 554, drop ceilings in rms.440,441,425 and426, 5th flr. west wing corridor receptacles and sconces, parking lot u.ground conduits to light poles also ok. (Light poles are pre cast)
|
Electrical Rough-In | 6/22/2015 | 6/22/2015 | 6/22/2015 | A | PASS |
Rex Boyles
|
|
|
4th floor unit drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 401, 408, 410, 411, 413, 414, 416, 443 and 444
|
Electrical Rough-In | 6/18/2015 | 6/18/2015 | 6/18/2015 | A | PASS |
Daryl DeGrange
|
|
|
5th floor corridors, stairwell "D" rough-in. Phone #: ###-#### Inspection requested via web by Rafael Castillo rough-in ok cover 5th floor corridors and stairwell "D"
|
Conference | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | DONE |
Daryl DeGrange
|
|
|
Discuss possibility of final on half of the residential units by August 15 and the other half at a later date. Phone #: ###-#### Inspection requested via web by Rafael Castillo Temporary occupancy would require approval from Project Management Ron Hill and Fire Marshall Romeo Gervais
|
Electrical Rough-In | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | PASS |
Daryl DeGrange
|
|
|
4th floor corridors, soffit ceilings (drops in units). Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough-in ok cover
|
Electrical Rough-In | 6/15/2015 | 6/15/2015 | 6/15/2015 | A | PASS |
Daryl DeGrange
|
|
|
Drop ceilings 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough-in ok cover drop ceilings in rooms 329,321,325,342 and service feeders shafts 421,425,431,433
|
Electrical Rough-In | 6/11/2015 | 6/11/2015 | 6/11/2015 | A | PASS |
Rex Boyles
|
|
|
Drop ceilings 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo already input info. did'nt go away 1st time
|
Final | 6/8/2015 | 6/8/2015 | 6/8/2015 | A | CANC |
Rex Boyles
|
|
|
5th floor unit rough in west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo needed r/i
|
Electrical Rough-In | 6/8/2015 | 6/8/2015 | 6/8/2015 | A | PASS |
Rex Boyles
|
|
|
5th floor unit rough in west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 521 thru 531
|
Electrical Rough-In | 6/1/2015 | 6/1/2015 | 6/1/2015 | A | PASS |
Rex Boyles
|
|
|
Drop ceiling rough in 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 225,231,233,242,344,343 and 309
|
Electrical Rough-In | 5/29/2015 | 5/29/2015 | 5/29/2015 | A | PASS |
Rex Boyles
|
|
|
4th floor units. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 421 thru 431, vent. shafts in rms. 422thru424 and 425 thru430
|
Electrical Rough-In | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Rex Boyles
|
|
|
4th floor units, drop ceilings 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 431 thru 442 and vent. shafts in rms. 436 and 432. Drop ceilings in rms. 305 thru 307, 311 thru313, 314,315,318 and 320.
|
Electrical Rough-In | 5/27/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Rex Boyles
|
|
|
2nd floor shaft inspection, 4th floor units inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok vent. shafts in rms. 225,231 and 233
|
Electrical Rough-In | 5/22/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Rex Boyles
|
|
|
Stairwell "B" inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok stairwell B 2 thru 5 and vent. shaft 242
|
Electrical Rough-In | 5/15/2015 | 5/18/2015 | 5/18/2015 | A | PASS |
Rex Boyles
|
|
|
Units rough-in 3rd floor west wing, shafts 2nd and 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok so. west wing rms. 221 thru230, vent. shafts in 232,234 thru 237, 239 and 332,334 thru 337 and 339 also ok
|
Electrical Rough-In | 5/15/2015 | 5/15/2015 | 5/15/2015 | A | PASS |
Rex Boyles
|
|
|
Rough-in shafts 3rd floor, units 3rd floor west, permanent service MMC#2. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok west wing 3rd flr rms. 331 thru 335, 337 thru 341 and partial on vent. shafts (see plans)
|
Electrical Rough-In | 5/12/2015 | 5/12/2015 | 5/12/2015 | A | PASS |
Rex Boyles
|
|
|
2nd floor drop ceilings, roof inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rm. soffits in 212,217,218,220,243 and 244. Also 2nd flr balcony ceiling ok to cover south half of west wing roof complete. OK to install nm cable now.
|
Electrical Rough-In | 4/16/2015 | 4/16/2015 | 4/16/2015 | A | PASS |
Rex Boyles
|
|
|
Inspection of 2 hour shafts east wing, stairwell "A". Roof over east wing progress. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok shafts in rms. 205, 213 thru 216. roof work on east should be complete friday(tomm). Rafael will keep checking and let us know when it's ready to continue electrical installation.
|
Electrical Rough-In | 4/15/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Rex Boyles
|
|
|
Shaft walls on 2nd floor for cover. Look over roof progress over east end of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial r/i ok 2 hr vent. shafts in rms. 202 thru 204, 206,211 and 212 NOTE: walk with Rafael to see if roof is complete on east wing and it is not done. No electrical wire in this area or any areas not dried in.
|
Electrical Rough-In | 3/20/2015 | 3/20/2015 | 3/20/2015 | A | PASS |
Rex Boyles
|
|
|
Rough-in west wing units. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 2nd floor west wing rooms
|
Conference | 1/22/2015 | 1/23/2015 | 1/23/2015 | A | DONE |
Rex Boyles
|
|
|
Discuss waterproofing of 4th level in order to expedite wiring rough in on levels 2 and 3. Phone #: ###-#### Inspection requested via web by Rafael Castillo ok to install nm cable in areas that are going to be waterproofed by McAlvain
|
Conference | 1/21/2015 | 1/21/2015 | 1/21/2015 | A | DONE |
Rex Boyles
|
|
|
Discuss panel clearances in units. Phone #: ###-#### Inspection requested via web by Rafael Castillo discuss hvac above loadcenters in each unit. Lea requesting to install nm cable now without roof done.
|
First Notice | 8/26/2015 | 8/26/2015 | | | |
Rex Boyles
|
|
|
|