First Notice | 10/4/2016 | 10/4/2016 | 7/19/2017 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Spencer McLean
|
Final | 10/4/2016 | 10/4/2016 | 10/4/2016 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Spencer McLean Receptacles installed for display of beds which change position. All complete at rough in. Final ok
|
Electrical Rough-In | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | PASS |
Rock A. Hudson
|
|
|
This is the mattress sales area in the SEARS department store. Phone #: ###-#### Inspection requested via web by Spencer McLean Receptacle additions all fished in. Called contractor to ask about whether came off existing circuit or added circuits, No answer. Rough in ok
|
Issue PAID IN FULL permit | | | 7/15/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/15/2015 | | DONE |
|
|
|
This permit was created on the web by Spencer McLean
|