First Notice | 3/15/2016 | 3/15/2016 | 10/18/2016 | | DONE |
Rock A. Hudson
|
|
|
|
Final | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a final inspection for tomorrow 3/15/16 for the AM. Our contact is Rod @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Seal offs poured. Final ok
|
Electrical Rough-In | 3/9/2016 | 3/10/2016 | 3/10/2016 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a temporary occupancy inspection for tomorrow in the AM for this project. Our contact is Rod @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate Interior of main sales office tested out so office furnishings can be moved in. Ok install main offices
|
Electrical Rough-In | 2/11/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
Eric Story
|
|
|
we are requesting a final for the warehouse only for this morning. Our contact is Rod @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate cieling in washbay electrical room ok cover
|
Electrical Rough-In | 2/8/2016 | 2/8/2016 | 2/8/2016 | P | PASS |
Rock A. Hudson
|
|
|
###-#### Rod Main offices grid rough in ok cover
|
Electrical Rough-In | 2/8/2016 | 2/8/2016 | 2/8/2016 | P | PASS |
Rock A. Hudson
|
|
|
###-#### Rod Wash bay hard lid rough in ok cover
|
Electrical Rough-In | 12/21/2015 | 12/22/2015 | 12/22/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a hard rock ceiling inspection for the bathroom for tomorrow 12/22/15 in the AM. Our contact is Rod @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Bathroom hardlid rough in ok cover
|
Electrical Rough-In | 12/17/2015 | 12/18/2015 | 12/18/2015 | A | PASS |
Daryl DeGrange
|
|
|
We are requesting a wall rough-in inspection for tomorrow 12/18/15 in the AM. Our contact is Rod ###-####, Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate rough-in ok cover walls
|
Electrical Rough-In | 11/5/2015 | 11/6/2015 | 11/6/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting an underground inspection at the propane station for tomorrow 11/6/15 in the AM. Our contact is Rod @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Rigid stub at pump location rough in ok cover
|
Electrical Rough-In | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PASS |
Daryl DeGrange
|
|
|
We are requesting a underground inspection for Monday 10/26/15 in the AM. Our contact is Rod @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate rough-in ok cover westside underground
|
Electrical Rough-In | 10/15/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Rock A. Hudson
|
|
|
We are requesting an underground inspection for the east side of the property and the parking lot for tomorrow 10/16/15 in the afternoon. Our contact is Rod @ ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Clint Tate 100% eastside, Front lot light towards road, underground rough in ok cover.
|
Electrical Rough-In | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting an inspection of our pole bases tomorrow 10/14/15 in the AM. Our contact is Rod @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate 3 pole bases rough in ok cover
|
Electrical Rough-In | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PASS |
Rock A. Hudson
|
|
|
Concrete encased on wash building and patial underground. ###-#### Concrete encases electrode and underground north side from meter area to north corners of building rough in ok cover
|
Electrical Rough-In | 10/2/2015 | 10/5/2015 | 10/5/2015 | A | CANC |
Rock A. Hudson
|
|
|
We are requesting a partial underground inspection and a ufer inspection at the washing bldg. for Monday 10/5/15 in the AM. Our contact is Rod @ ###-####. Thank you, Phone #: ###-#### Inspection requested via web by Clint Tate Needed PM inspection, rescheduled
|
Permanent Service | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a service inspection for tomorrow 9/22/15 in the AM. Our onsite contact is Rod @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate p/s u/g n ok
|
Issue PAID IN FULL permit | | | 9/11/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/11/2015 | | DONE |
|
|
|
This permit was created on the web by Clint Tate
|