First Notice | 10/23/2015 | 10/23/2015 | 10/30/2015 | | DONE |
Rock A. Hudson
|
|
|
This permit finaled on the web by Clint Tate
|
Final | 10/22/2015 | 10/23/2015 | 10/23/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a final inspection for tomorrow 10/23/15 in the AM. Our contact is Rich ###-#### or Cary @ ###-####. Thank you Phone #: ###-#### Inspection requested via web by Clint Tate Access provided for transformer above grid. Final ok
|
Electrical Rough-In | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PASS |
Rock A. Hudson
|
|
|
We are requesting a wall rough-in inspection for tomorrow 9/17/15 in the AM. Our onsite contact is Rich @ ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Attached to BLD15-03098 .Check above demizing wall disconnect for transformer is still with in sight of. Demizing wall rough in ok cover
|
Electrical Rough-In | 9/11/2015 | 9/14/2015 | 9/14/2015 | P | CANC |
Rock A. Hudson
|
|
|
We are requesting a wall rough-in inspection for Monday 9/14/15 in the afternoon. Our onsite contact is Rich ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Building permit has not been purchaced yet contractor will reschedule when building permit exists.
|
Issue PAID IN FULL permit | | | 9/11/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/11/2015 | | DONE |
|
|
|
This permit was created on the web by Clint Tate
|