Final | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PASS |
Rock A. Hudson
|
|
|
The job site is in the Truss Plant in the northwest corner of the property. The finish roller is located inside the building on the center of the south wall. If you have questions call Dan at ###-#### Phone #: ###-#### Inspection requested via web by Dan Mitchell Final ok
|
Electrical Rough-In | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | PASS |
Rock A. Hudson
|
|
|
The job site is in the Truss Plant in the northwest corner of the property. The finish roller is located inside the building on the center of the south wall. If you have questions call Dan at ###-#### Phone #: ###-#### Inspection requested via web by Dan Mitchell Rough in ok
|
Issue PAID IN FULL permit | | | 9/16/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 9/16/2015 | | DONE |
|
|
|
This permit was created on the web by Dan Mitchell
|
First Notice | 9/17/2015 | 9/17/2015 | | | |
Rock A. Hudson
|
|
|
|