Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberELE15-03238
StatusFinaled
Name PERSISTENCE CORP
Site Address 1120 W CHAMBERLIN ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration or Repair: Install a new 200 Amp overhead service at a new location & add 2 new sub-panels - 125 Amp & 200 Amp. Permits for wiring all circuits out of the sub-panels will be pulled later.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final9/23/20169/23/20169/23/2016PPASS
DetailsJames Ady
Please inspect the Main Service to the interior sub panels. I believe I''ve made the additions I was missing at rough in: Grounding bridge, irreversible grounding connections to the ground rod, water pipe, etc. from the old service grounds. Home owner has pulled permits for the interior branch circuits. Phone #: ###-#### Inspection requested via web by nathan palmer Corrections to main service made.Final ok
Final11/18/201511/18/201511/18/2015AFAIL
DetailsRex Boyles
Please inspect the service sub-panel wiring ; GFCI circuits below those 2 panels. Re-using existing ground rod ; water pipe grounding beyond the existing service location. (Please let me know if I need to feed the 125A breaker from the load side of the 200A breaker inside the Meter Main panel. It was wired internally different than I expected so what you see is not what I originally envisioned.) Phone #: ###-#### Inspection requested via web by nathan palmer NOTES: 4/0 ser ok IF not surrounded by insulation in ceilig. OK to insulate walls only for the short run as per 338.10(4) and 310.15(2). Confirm and expose location of existing grounding electrodes and conductors or add 2 ground rods as per NEC 250.52(5). Install intersystem ground termination bar as per 250.94. Confirm buss rating for 125amp breaker installed in service equipment. Not clear on label on panel door. Install plastic bushings on romex connectors with conductors larger than #4.. Needed p/s today, not final
Permanent Service11/18/201511/18/201511/18/2015PPASS
DetailsRex Boyles
Please inspect the service sub-panel wiring ; GFCI circuits below those 2 panels. Re-using existing ground rod ; water pipe grounding beyond the existing service location. (Please let me know if I need to feed the 125A breaker from the load side of the 200A breaker inside the Meter Main panel. It was wired internally different than I expected so what you see is not what I originally envisioned.) Phone #: ###-#### Inspection requested via web by nathan palmer p/s o/h rec ok
Issue PAID IN FULL permit  10/7/2015 DONE
Payment received via Govolutions
Application received  10/7/2015 DONE
This permit was created on the web by nathan palmer